Improve building at base lift 1; loading area at lift 2; and portions of runs including Bambi, Lower Bambi, Rolling Rock, and Gamble Trees. Install 815' snowmaking line in Gamble Trees run. All projects in existing special use permit boundary.
Location
Within the bounds of the Sipapu Ski Area
Project timeline
1
Scoping Start
07/10/2012
2
Comment Period
07/12/2012
3
Decision
09/2012 (Estimated)
4
Implementation
10/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| 2012 Sipapu SKi Area Summer Projects Decision Memo | Decision Signed Date: 09/05/2012 Legal Notice Date: 09/13/2012 |
| Forests | Carson National Forest |
| Districts | Camino Real Ranger District |
| Legal Land Description | T. 22N, R. 13E, sections 10 and 15 |