The Forest Service is proposing to approve an application for a special use authorization, submitted by JMEC. The special use authorization would allow JMEC to operate and maintain an existing 14.4 Kilovolt (KV) power line system.
Location
Lopez Canyon, Manuel Canyon, Mestenas Mesa, and Vigas Canyon
Project timeline
1
Scoping Start
09/01/2012
2
Comment Period
09/13/2012
3
Decision
07/2013 (Estimated)
4
Implementation
08/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Jemez Mountains Electric Coop., Inc. Electric Transmission Line Permit | Decision Signed Date: 07/09/2013 Legal Notice Date: 07/25/2013 |
| Forests | Carson National Forest |
| Districts | Jicarilla Ranger District |
| Legal Land Description | Section 8, T27N, R4W, New Mexico Principal Meridian (NMPM), Section 31, T30N, R4W, NMPM. Sections 11, 14, 23, 26, and 35, T30N, R5W, NMPM |