Replacement of existing water line beginning at a private land well near Columbine Campground and running northeast along NM Hwy 38 through National Forest to the mill site on private land. A new special use authorization would be issued for the line
Location
Existing utility corridor near Columbine Campground northeast along NM Hwy 38
Project timeline
1
Scoping Start
07/25/2013
2
Comment Period
07/25/2013
3
Decision
09/2013 (Estimated)
4
Implementation
10/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Chevron Mining, Inc. Water Line | Decision Signed Date: 09/04/2013 Legal Notice Date: 09/12/2013 |
| Forests | Carson National Forest |
| Districts | Questa Ranger District |
| Legal Land Description | T28N, R13E, Section 1, 11, and 12 and T28N, R14E, Section 6 |