Repair and establish drainage structures along 4 miles of existing motorized trail. Construct a 100 ft. by 100 ft. parking area at the north trailhead, grade and surface the south trailhead. Install barriers to prevent full-size vehicle use of trail.
Location
T. 24N, R. 15E, sections 2-4, 11, and 14; T. 25, R. 15E, section 33
Project timeline
1
Scoping Start
02/14/2013
2
Comment Period
02/14/2013
3
Decision
04/2013 (Estimated)
4
Implementation
05/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management |
| Forest Trail 70 Improvement Project | Decision Signed Date: 04/09/2013 Legal Notice Date: 04/18/2013 |
| Forests | Carson National Forest |
| Districts | Camino Real Ranger District |