Reissue 24 expired or expiring long-term permits for land uses on the Carson National Forest. There will be no change to the facilities or activities authorized in the permits.
Location
Carson National Forest
Project timeline
1
Scoping Start
04/22/2015
2
Decision
07/2016 (Estimated)
3
Implementation
07/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forest-wide Reissuance of Expired Lands Special Use Permits | Decision Signed Date: 07/27/2016 |
| Forests | Carson National Forest |
| Districts | Carson National Forest All Units |
| Legal Land Description | Not Applicable |