Install a fixed, remotely-operated avalanche control system within avalanche prone areas west of Kachina Peak along and below the ridgeline. This system would improve public and ski patrol safety within TSV, Inc.'s existing permit boundary.
Location
Within the existing special use permit boundary held by Taos Ski Valley, Inc.
Project timeline
1
Scoping Start
06/23/2016
2
Decision
05/2018 (Estimated)
3
Implementation
05/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Taos Ski Valley Gazex Avalanche Mitigation System Installation | Decision Signed Date: 05/03/2018 |
| Forests | Carson National Forest |
| Districts | Questa Ranger District |
| Legal Land Description | T27N, R14E, section 21 |