Reissue approximately 15 long-term permits for land uses on the Carson National Forest. There will be no change in the facilities or activities authorized in the permits.
Location
Various locations on the Carson National Forest
Project timeline
1
Scoping Start
02/01/2018
2
Decision
06/2018 (Estimated)
3
Implementation
06/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forest-wide Reissuance of Lands Special Use Permits 2018 | Decision Signed Date: 06/05/2018 |
| Forests | Carson National Forest |
| Districts | Carson National Forest All Units |
| Legal Land Description | Not Applicable |