The activities planned are to widen a section of FSR 132 to eliminate or soften a blind corner of a banked turn/ intersection. The project would require vegetation removal and cut fill of road base material to widen the road and approach to the curve
Location
The project location is in the community of Lama on the Questa Ranger District-FSR 132.
Project timeline
1
Scoping Start
10/16/2023
2
Decision
11/2023 (Estimated)
3
Implementation
12/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (24), 36 Cfr 220.6(E)(24) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction |
| Upper Lama Road Improvement | Decision Signed Date: 11/15/2023 |
| Forests | Carson National Forest |
| Districts | Questa Ranger District |
| Legal Land Description | Township 28 North, Range 12 East section 24 |