Approximately 9 miles of new 345kV electric transmission line connecting a new wind park located on Flying M Ranch private property and State lands to the existing Western Area Power Authority (Western) 345kV line. Western will be taking lead on NEPA
Location
Proposed new utility corridor located along Forest Road 125 from the eastern Forest boundary to the existing 345-kV tranmission line.
Project timeline
1
NOI in Federal Register
07/24/2009
2
DEIS NOA in Federal Register
07/23/2010
3
FEIS NOA in Federal Register
06/03/2012
4
Decision
05/2012 (Estimated)
5
Implementation
07/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Forest Service Energy Implementation Plan |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Grapevine Canyon Wind Project | Decision Signed Date: 05/22/2012 Legal Notice Date: 06/03/2012 |
| Forests | Coconino National Forest |
| Districts | Flagstaff Ranger District |
| Legal Land Description | T18N, R10E and T18N, R11E. Anderson Mesa. |