Proposal by Arizona Public Service to replace a buried powerline from Lake Mary Road to Hwy 87 and along Forest Road 632 and 9033H east of Clints Well. This line replaces a failing existing buried line with minor realignments.
Location
Along Forest Highway 3 Lake Mary Road from Hwy 87 to Happy Jack Lodge
Project timeline
1
Scoping Start
08/10/2015
2
Decision
11/2015 (Estimated)
3
Implementation
11/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| APS 21kV Clints Well (BR-12)Distribution Line Reconstruction Project | Decision Signed Date: 11/01/2015 |
| Forests | Coconino National Forest |
| Districts | Mogollon Rim Ranger District |
| Legal Land Description | Not Applicable |