Proposal to construct approximately 21 miles of new 69kV power line along the Western Area Power 345 kV lines from Youngs Substation south of I-40 to Forest Road 125 to a new substation on federal land south of Mormon Lake.

Location

Along the 345kV power line and FR 125 south of I40 and east of Lake Mary Road

Project timeline

1
Scoping Start
04/09/2013
2
Comment Period
06/18/2014
3
Objection Period Start
08/29/2014
4
Decision
11/2014 (Estimated)
5
Implementation
12/2014 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
APS NO1 Youngs Canyon To Mormon Lake 69kV Power Line And Substation ProjectDecision Signed Date: 11/07/2014
ForestsCoconino National Forest
DistrictsFlagstaff Ranger District
Legal Land DescriptionT21N, R9E, Section 24 to T18N. R9E, Section 28, G&SRM