The City of Flagstaff, has requested authorization to construct and bury a new 8 inch diameter water line within the Lake Mary Well Field Area and construct a new vehicle and equipment shed at the Lake Mary Water Treatment Plant.
Location
Water line installation is in the Lake Mary well field area just south of Flagstaff City limits adjacent to FH3. The equipment shde would be built in the existing Lake Mary water treatment plant.
Project timeline
1
Scoping Start
06/24/2014
2
Decision
08/2014 (Estimated)
3
Implementation
09/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| City of Flagstaff 2014 Projects | Decision Signed Date: 08/27/2014 |
| Forests | Coconino National Forest |
| Districts | Coconino National Forest All Units |
| Legal Land Description | Not Applicable |