Rehabilitate and upgrade the water and phone/IT system at Sunset Crater Volcano National Monument. The project consists of the general construction of underground potable water mains and a phone/IT conduit will also be installed.
Location
This project is located within Sunset Crater Volcano National Monument with work located at the Visitor Center area and the Lava Flow trailhead.
Project timeline
1
Scoping Start
07/13/2015
2
Decision
08/2015 (Estimated)
3
Implementation
01/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Sunset Crater National Monument Waterline Replacement | Decision Signed Date: 08/31/2015 |
| Forests | Coconino National Forest |
| Districts | Flagstaff Ranger District |
| Legal Land Description | Not Applicable |