Western is proposing to implement a operation and maintenance (O&M) and Integrated Vegetation Management (IVM) program on the Rogers-Glen Canyon section of the Colorado River Storage Project (CRSP) Transmission System. Includes use of herbicides.
Location
This transmission line runs throughout the Coconino National Forest and through portions of the Tonto National Forest.
Project timeline
1
Scoping Start
04/20/2016
2
Comment Period
08/2023 (Estimated)
3
Objection Period Start
02/2024 (Estimated)
4
Decision
07/2024 (Estimated)
5
Implementation
07/2024 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other; Nepa Document Prepared By Another Federal Agency |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Electric Transmission; Special Use Authorizations; Plan Amendment; Noxious Weed Treatments |
| Forests | Coconino National Forest; Tonto National Forest |
| Districts | Coconino National Forest All Units; Tonto National Forest All Units |
| Legal Land Description | Not Applicable |