City of Flagstaff is proposing to obtain a permit to construct a portion of the Flagstaff Urban Trail System 10 foot wide aggregate trail with 2 foot native shoulders to complete section of the trail system. Drainage work on Highway Stock tank.
Location
From JW Powell to connect to a culvert that crosses under I-17 toward Fort Tuthill outside of Flagstaff. T20N, R7E, Section 5
Project timeline
1
Scoping Start
10/01/2019
2
Decision
11/2019 (Estimated)
3
Implementation
05/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Sheep Crossing Trail-FUTS Trail Additions | Decision Signed Date: 11/12/2019 |
| Forests | Coconino National Forest |
| Districts | Flagstaff Ranger District |
| Legal Land Description | Not Applicable |