Restoration of Oak Creek Watershed, as a follow to the 2016 Middle and Lower Oak Creek Canyon Watershed Restoration Action Plan. Click on "Analysis" tab to view the July 24, 2019 EA and on the "Decision" tab to view the Sept. 20, 2019 decision notice
Location
Upper, Middle and Lower Oak Creek watersheds
Project timeline
1
Scoping Start
12/22/2017
2
Comment Period
08/03/2018
3
Objection Period Start
07/24/2019
4
Decision
09/2019 (Estimated)
5
Implementation
11/2019 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Watershed Improvements |
| Oak Creek Watershed Restoration Project | Decision Signed Date: 09/20/2019 |
| Forests | Coconino National Forest |
| Districts | Red Rock Ranger District |
| Legal Land Description | T18N R6E; T18N R5E; T17N R6E; T17N R5E; T17N R4E; T16N R6E; T16N R5E; T16N R4E; T15N R4E; T15N R65 |