Construction of three equipment shelters and replacement of two generators,chain link fence and existing guyed tower with self supporting tower. This would all occur within the existing communication site boundary.
Location
1/4 mile off Highway 87, approximately 4 miles south of intersection of Hwy 87 and Hwy 260 on the west Mogollon Rim.
Project timeline
1
Scoping Start
03/2021 (Estimated)
2
Decision
06/2021 (Estimated)
3
Implementation
07/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance |
| Forests | Coconino National Forest |
| Districts | Mogollon Rim Ranger District |
| Legal Land Description | Not Applicable |