construction of a new concrete pad, generator, and propane tank at the SBA Tower on Mount Elden.
Location
Mount Elden Communication Site
Project timeline
1
Scoping Start
06/18/2020
2
Decision
09/2020 (Estimated)
3
Implementation
09/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| SBA Communication Site improvements, Mount Elden | Decision Signed Date: 09/01/2020 |
| Forests | Coconino National Forest |
| Districts | Flagstaff Ranger District |
| Legal Land Description | Not Applicable |