Project timeline

1
Scoping Start
06/18/2020
2
Decision
09/2020 (Estimated)
3
Implementation
09/2020 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
SBA Communication Site improvements, Mount EldenDecision Signed Date: 09/01/2020