Stabilize a portion of the Cave Springs streambank along Oak Creek by replacing a grouted rip-rap structure with a stepped, concrete wall. Project to also stabilize a low-water crossing along the Cave Springs Campground access road.
Location
Section 34, T 19N, R 6E
Project timeline
1
Scoping Start
05/25/2020
2
Decision
03/2023 (Estimated)
3
Implementation
05/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Road Maintenance; Road Improvements/Construction |
| Cave Springs Streambank Stabilization | Decision Signed Date: 03/24/2023 |
| Forests | Coconino National Forest |
| Districts | Red Rock Ranger District |
| Legal Land Description | Not Applicable |