ADOT to stockpile clean fill dirt at Kelly Canyon Pit.
Location
section 25, Township 20N, Range 06E at Kelly Canyon pit.
Project timeline
1
Scoping Start
01/27/2022
2
Decision
06/2022 (Estimated)
3
Implementation
07/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Special Use Authorization, Kelly Canyon Pit Stockpile Site | Decision Signed Date: 06/30/2022 |
| Forests | Coconino National Forest |
| Districts | Flagstaff Ranger District |
| Legal Land Description | Not Applicable |