Install fiber optic cable on an existing APS power line between Magdalena Road and the Basecamp at Snowbowl.
Location
Located along Highway 180 between Magdalena Road and the Snowbowl Basecamp at the bottom of Forest Road 516.
Project timeline
1
Scoping Start
06/14/2022
2
Decision
08/2022 (Estimated)
3
Implementation
09/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Snowbowl Fiber Reinforcement Project (Centurylink Project N.804226) | Decision Signed Date: 08/24/2022 |
| Forests | Coconino National Forest |
| Districts | Flagstaff Ranger District |
| Legal Land Description | Not Applicable |