Centurylink will install approx. 6400 feet of fiberoptic cable in existing conduit along Hwy 179 headed south to the Red Rock R.D. and splice fiberline into F.S. office. One concrete tele-comm pedestal adjacent to the office will be replaced.
Location
Beginning at Ridgeway Dr. and Hwy 179 in the Village of Oak Creek moving south along the Hwy 179 corridor ending at 8375 Hwy 179 (RedRock R.D. office)
Project timeline
1
Scoping Start
02/06/2023
2
Decision
05/2023 (Estimated)
3
Implementation
07/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Qwest Corp. D/B/A CenturyLink QC | Decision Signed Date: 05/01/2023 |
| Forests | Coconino National Forest |
| Districts | Red Rock Ranger District |
| Legal Land Description | Not Applicable |