UNS is requesting permission to install a natural gas spur line to provide gas from their mainline running through Coconino NF to private property. The 3/4 inch pipeline would be buried 3.5ft deep and cross 33ft of Coconino NF lands.
Location
Project area is on Coconino National Forest Land immediately east of 990 Old Munds Highway Flagstaff AZ
Project timeline
1
Scoping Start
10/13/2023
2
Decision
02/2024 (Estimated)
3
Implementation
03/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Unisource Gas (UNS) Old Munds Highway Natural Gas Pipeline Spur | Decision Signed Date: 02/15/2024 |
| Forests | Coconino National Forest |
| Districts | Flagstaff Ranger District |
| Legal Land Description | Not Applicable |