Replace restrooms, renovate picnic sites and trailheads, install vehicular bridges over stream, naturalize stream channel, and improve roads and parking areas.
Location
Marshall Gulch Picnic Area and Trailhead
Project timeline
1
Scoping Start
03/19/2010
2
Comment Period
11/03/2017
3
Objection Period Start
05/21/2018
4
Decision
07/2018 (Estimated)
5
Implementation
01/2019 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management |
| Marshall Gulch Picnic Area and Trailhead Improvements | Decision Signed Date: 07/17/2018 |
| Forests | Coronado National Forest |
| Districts | Santa Catalina Ranger District |
| Legal Land Description | Sec 31, T 11 S, R 16 E |