The Forest proposes to replace 4 miles of pipeline and add 2 storage tanks and several troughs on the H6, Sausito, Heifer and Caralampio pastures of the Marstellar allotment.
Location
Marstellar Allotment:H6, Sausito, Heifer and Caralampio pastures
Project timeline
1
Scoping Start
07/02/2013
2
Comment Period
07/02/2013
3
Decision
08/2013 (Estimated)
4
Implementation
09/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Grazing Allotment Management |
| H6 Water System, Wildlife Habitat Improvement Project | Decision Signed Date: 08/14/2013 |
| Forests | Coronado National Forest |
| Districts | Nogales Ranger District |
| Legal Land Description | Sec 24 and 25 , T23S, R12E; and Sec19 and 30, T23S R13E |