Decision Memo Completed

Road Construction (5 miles) - Customs and Border Protection

Coronado National Forest Cochise, Arizona Nogales Ranger District

Provide improved access to the U.S./Mexico border on the Coronado National Forest by constructing approximately 5 miles of roads that will enable CBP to safely and effectively execute its mission while protecting the forest natural resource.

Location

3 Different Locations: Fresnal Wash area, Cantinas Reservoir area,Sycamore Canyon area

Project timeline

1
Scoping Start
01/03/2014
2
Decision
05/2017 (Estimated)
3
Implementation
01/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Improvements/Construction
Road Construction (5 miles) - Customs and Border ProtectionDecision Signed Date: 05/25/2017
ForestsCoronado National Forest
DistrictsNogales Ranger District
Legal Land DescriptionNot Applicable
Road management