To construct approximately 2,000 feet (approximately .37 miles) of trail to provide connectivity between the Cunningham Loop and FR507 and an interconnection with in the loop.
Location
Cunningham Loop and FR507
Project timeline
1
Scoping Start
06/01/2015
2
Decision
06/2015 (Estimated)
3
Implementation
06/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Cunningham Loop Connect-A-Trail Project | Decision Signed Date: 06/09/2015 |
| Forests | Coronado National Forest |
| Districts | Safford Ranger District |
| Legal Land Description | Section 3 and 11, Township 9 South, Range 24 East, GSRM. |