Reissuance of an existing special use permit to the City of Tombstone for the operations and maintenance of four spring developments and water transmission line located inside the Miller Peak Wilderness.
Location
Sections 10, 11, 12, 13, 14, 15, 23, 24, and 26, Township 23 South, Range 20 East, and Sections 7 and 18, Township 23 South, Range 21 East
Project timeline
1
Scoping Start
10/01/2015
2
Decision
08/2016 (Estimated)
3
Implementation
09/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| City of Tombstone Water Special Use Permit Reissuance | Decision Signed Date: 08/09/2016 |
| Forests | Coronado National Forest |
| Districts | Sierra Vista Ranger District |
| Legal Land Description | Not Applicable |