Decision Memo Completed

Carr Barn Dip Site Creation

Coronado National Forest Cochise, Arizona Sierra Vista Ranger District

Expanding Carr pond to increase the amount of surface water in the area, and installing a water storage tank to rapidly refill the pond if it is used during fire suppression. The pond would be created just south of the existing frog pond.

Location

Carr Pond, Huachuca Mountains

Project timeline

1
Scoping Start
03/10/2017
2
Decision
04/2017 (Estimated)
3
Implementation
05/2017 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements
Carr Barn Dip Site CreationDecision Signed Date: 04/07/2017
ForestsCoronado National Forest
DistrictsSierra Vista Ranger District
Legal Land DescriptionSection 7, 23S, 21E
Wildlife, fish, rare plants