TEP will develop five-year plan for utility pole replacement as a component of their special use permit authorization to operate on the Nogales Ranger District.
Location
Multiple areas across the Nogales Ranger District.
Project timeline
1
Scoping Start
02/20/2017
2
Decision
10/2019 (Estimated)
3
Implementation
11/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| TEP Five-Year Plan | Decision Signed Date: 10/30/2019 |
| Forests | Coronado National Forest |
| Districts | Nogales Ranger District |
| Legal Land Description | Section 12, T19 S, R 15 E, Sections 17, 18, 20, 21, 27, 28, and 34, T 19 S, R 16 E |