The proposal is to upgrade a Tucson Electric Power Company existing electrical service line (13.8 KV, 3-phase electric) to the Sabino Canyon Recreation Maintenance Yard.
Location
T13S, R15E, SW 1/4 of Section 9
Project timeline
1
Scoping Start
12/20/2018
2
Decision
03/2019 (Estimated)
3
Implementation
04/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction |
| Tucson Electric Power Company (TEP) Sabino Canyon Line Upgrade | Decision Signed Date: 03/18/2019 |
| Forests | Coronado National Forest |
| Districts | Santa Catalina Ranger District |
| Legal Land Description | Not Applicable |