Decision Memo Completed

UNSE/TEP Mt. Hopkins Substation Erosion Control

Coronado National Forest Santa Cruz, Arizona Coronado National Forest All Units

Erosion repair of existing substation site to place a concrete slope protection with welded wire fabric and replace existing chain link fence on south fence-line.

Location

Mt. Hopkins Substation

Project timeline

1
Scoping Start
07/07/2022
2
Decision
08/2022 (Estimated)
3
Implementation
08/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
UNSE/TEP Mt. Hopkins Substation Erosion ControlDecision Signed Date: 08/16/2022
ForestsCoronado National Forest
DistrictsNogales Ranger District
Legal Land DescriptionT20S, R14E, SW 1/4 of SE 1/4 of Sec. 14
Special area management