Due to major erosion, approx. 0.11 miles of NFSR 345 needs to be realigned between 1-10 feet from the existing road matrix. Gabion baskets or metal netting would be added to the eroded (NW) side of the road to avoid further damage to the road matrix.
Location
31.8587974061, -109.959874549 (approx 0.2 miles East from NFSR 345 and 4825 junction)
Project timeline
1
Scoping Start
03/02/2023
2
Decision
04/2023 (Estimated)
3
Implementation
05/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (24), 36 Cfr 220.6(E)(24) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction |
| Middlemarch Road Realignment | Decision Signed Date: 04/05/2023 |
| Forests | Coronado National Forest |
| Districts | Douglas Ranger District |
| Legal Land Description | 18S, 23 E, Sec 23 NE 1/4 |