Operation and maintenance of a water pipeline that carries water from the Rhem adit to private property. Current pipeline is constructed of 2.5 inch PVC aboveground approximately 2,500 feet in length with 10 feet wide right of way.
Location
East Whitetail Canyon, Rhem Tunnel
Project timeline
1
Scoping Start
10/25/2024
2
Decision
10/2024 (Estimated)
3
Implementation
11/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Water Transmission Line Permit - Whitetail Ventures LLC Rhem Tunnel | Decision Signed Date: 10/30/2024 |
| Forests | Coronado National Forest |
| Districts | Douglas Ranger District |
| Legal Land Description | T16S, R30E, Sec. 33 |