Installation of a fiber optic line within the existing Tranwestern ROW. ROW width of 8 feet. Lenght will equal 51,135 feet. Total of 9.391 acres
Location
Drake to Ashfork within Kaibab NF boundaries.
Project timeline
1
Scoping Start
10/29/2015
2
Decision
01/2016 (Estimated)
3
Implementation
01/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| CenturyLink Fiber Optic Line Installation | Decision Signed Date: 01/08/2016 |
| Forests | Kaibab National Forest |
| Districts | Williams Ranger District |