Extend pipeline from Power Line Storage Tank (#001920) in Miller Pasture to Fix Tank located in the NW corner of the pasture. New pipeline would be about 1.5 miles long length, constructed of 1.5" diam. HDPE poly-pipe buried 30" deep.
Location
T 25N, R 3E, Sections 1 and 12
Project timeline
1
Scoping Start
02/15/2017
2
Comment Period
05/03/2017
3
Objection Period Start
06/14/2017
4
Decision
08/2017 (Estimated)
5
Implementation
08/2017 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Structural Improvements |
| Miller Pasture Water Pipeline Extension | Decision Signed Date: 08/07/2017 |
| Forests | Kaibab National Forest |
| Districts | Williams Ranger District |
| Legal Land Description | Not Applicable |