A proposal from CommNet for fiber optic cable to provide high-speed internet to the Grand Canyon USD buildings crossing the Williams and Tusayan Ranger Districts, the cable will go on existing utility poles, or be buried along existing roadways
Location
Williams and Tusayan Ranger Districts
Project timeline
1
Scoping Start
04/06/2020
2
Decision
05/2020 (Estimated)
3
Implementation
07/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| GCUSD Fiber Optic Line | Decision Signed Date: 05/05/2020 |
| Forests | Kaibab National Forest |
| Districts | Williams Ranger District |
| Legal Land Description | Not Applicable |