To provide reliable and efficient water delivery to the City of Williams. An alternate dual water line alignment, totaling approx. 0.8 mi, with access road improvement, is being considered to replace approx. 1 mi of the alignment approved in 2020.
Location
Southeast of the City of Williams parallel to Dogtown Wash
Project timeline
1
Scoping Start
03/12/2021
2
Comment Period
03/12/2021
3
Objection Period Start
05/04/2021
4
Decision
07/2021 (Estimated)
5
Implementation
07/2021 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Dogtown Waterline Project Alternate Alignment Supplemental EA | Decision Signed Date: 07/06/2021 |
| Forests | Kaibab National Forest |
| Districts | Williams Ranger District |
| Legal Land Description | T21N, R3E, Section 6, Gila and Salt River Meridian |