Project timeline

1
Scoping Start
04/27/2021
2
Decision
06/2021 (Estimated)
3
Implementation
07/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Decision Memo, GCUSD Fiber Optic Line Revised AlignmentDecision Signed Date: 06/07/2021
ForestsKaibab National Forest
DistrictsWilliams Ranger District; Tusayan Ranger District
Legal Land DescriptionNot Applicable
Special use management