Authorize installation of an underground fiber optic line between Paulden and Ashfork, Arizona. Approximately 9.58 miles would be on the Williams Ranger District and would be within the Highway 89 right-of-way.
Location
Within the Highway 89 right-of-way between Paulden and Ash Fork
Project timeline
1
Scoping Start
05/19/2021
2
Decision
07/2021 (Estimated)
3
Implementation
07/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Arcadian Fiber Optic Line | Decision Signed Date: 07/26/2021 |
| Forests | Kaibab National Forest |
| Districts | Williams Ranger District |
| Legal Land Description | Not Applicable |