Install a new water pipeline between the Town of Tusayan and the Tusayan Ranger District compound to provide a reliable water source to the ranger station and associated administrative facilities/housing.
Location
Parallel to the east side of Highway 64 north of the Town of Tusayan
Project timeline
1
Scoping Start
10/20/2021
2
Decision
02/2022 (Estimated)
3
Implementation
02/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Tusayan Ranger Station Waterline Connection | Decision Signed Date: 02/16/2022 |
| Forests | Kaibab National Forest |
| Districts | Tusayan Ranger District |
| Legal Land Description | T30N, R2E, Sections 13 & 24, Gila and Salt River Meridian |