Work to prepare Grandview Lookout Cabin for use as a cabin rental. Activities include roof and paint hazmat abatement, solar panel installation, a new gravel path to the existing vault toilet, greywater system installation, and other upgrades.
Location
Adjacent to Grandview Lookout Tower off of Forest Road 310
Project timeline
1
Scoping Start
09/01/2021
2
Decision
07/2022 (Estimated)
3
Implementation
09/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Facility Maintenance |
| Decision Decided Date | 07/08/2022 |
| Forests | Kaibab National Forest |
| Districts | Tusayan Ranger District |
| Legal Land Description | T30N, R4E, Section 27, Gila and Salt River Meridian |