Exchange up to approx. 0.94 ac of private land for up to approx. 0.94 ac of adjacent FS land to allow construction of drainage features to mitigate flood risk posed by Railroad Tank Dam. Flood risk mitigation analyzed in separate 2017 NEPA.
Location
Approximately 3.9 miles west of the Bellemont/I-40 interchange, immediately north of I-40 in Railroad Tank Draw.
Project timeline
1
Scoping Start
11/17/2021
2
Decision
09/2023 (Estimated)
3
Implementation
09/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (7), 36 Cfr 220.6(D)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Land Exchanges |
| Forests | Kaibab National Forest |
| Districts | Williams Ranger District |
| Legal Land Description | T22N, R5E, Section 32, Gila and Salt River Meridian |