Decision Memo Completed

Salt River Project Monitoring Permit Amendment

Kaibab National Forest Coconino, Arizona Williams Ranger District

Amend Special Use Authorization KA194 Amendment #2, issued to Salt River Project (SRP), to allow for relocation of flow monitoring devices 150 yards upstream of their existing location because of damage caused by the Rafael Fire in 2021.

Location

Outside of Sycamore Canyon Wilderness off of Forest Road 110

Project timeline

1
Scoping Start
01/19/2022
2
Decision
03/2022 (Estimated)
3
Implementation
04/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Salt River Project Monitoring Permit AmendmentDecision Signed Date: 03/11/2022
ForestsKaibab National Forest
DistrictsWilliams Ranger District
Legal Land DescriptionT19N, R4E, Sec. 5