Reroute the Flume trail, adding new segments, so that it becomes one continuous route that does not require shared mixed use with the Red Cloud Loop Scenic Backway.
Location
Dry Fork Flume Trail
Project timeline
1
Scoping Start
09/29/2008
2
Decision
04/2010 (Estimated)
3
Implementation
06/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management; Travel Management |
| Dry Fork Canyon Flume Trail Reroute | Decision Signed Date: 04/09/2010 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | 40?368N, 109?4433W and 40?3635N, 109?4513W and 40?3645N, 109?4523W |