Environmental Assessment · Flaming Gorge Ranger District · updated 2/3/2026
The Buckboard Marina is approximately 22 miles south of Green River, WY off of Highway 530. · Sweetwater, Wyoming
We are proposing to adjust the boundary of the Buckboard Marina's special use permit to remove water acreage and potentially add areas of land to the south and east.
Special use management
Scoping Start
02/2026 (Estimated)
Comment Period
02/2026 (Estimated)
Objection Period Start
04/2026 (Estimated)
Decision
06/2026 (Estimated)
Implementation
06/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Sec. 28, T. 15 N., R. 108 W., 6th principal meridian |
Decision Memo · Vernal Ranger District · updated 11/25/2025
Diamond Mountain area on the Vernal Ranger District · Uintah, Utah
This project is a duplicate of #68806.
Grazing managementMinerals and geology
Decision
11/2025 (Estimated)
Implementation
11/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Allotment Management; Minerals Or Geology Plans Of Operations; Grazing Structural Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Environmental Impact Statement · Flaming Gorge Ranger District · updated 5/2/2025
The original proposed action included a water line across the northern end of the Flaming Gorge National Recreation Area on USFS-managed lands south of Green River, WY. · Sweetwater, Wyoming
The BLM issued their decision selecting Alternative D on 5/2/2025: https://eplanning.blm.gov/eplanning-ui/project/2016395/510. Alternative D does not involve any USFS lands so the USFS portion of the project is cancelled.
Minerals and geologySpecial use management
NOI in Federal Register
04/28/2022
DEIS NOA in Federal Register
08/09/2024
FEIS NOA in Federal Register
02/28/2025
Objection Period Start
06/2025 (Estimated)
Decision
09/2025 (Estimated)
Implementation
09/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations; Minerals Or Geology Plans Of Operations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 5/2/2025
Ashley National Forest · Daggett; Duchesne; Uintah, Utah
This master permit would consolidate all of Moon Lake Electric's powerlines under one permit and would establish a standardized 50-foot right-of-way for all their overhead and buried powerlines on the Ashley National Forest.
Special use management
Decision
04/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | B4.13 |
| Special Authority | Forest Service Energy Implementation Plan |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Ashley National Forest All Units |
| Legal Land Description | T2N R24E R23E R22E R21E T1N R22E T1S R22E T3N R2W T2N R2W T2N R4W T2N R5W T2N R6W T2N R7W T2N R8W T1N R8W T1N R9W T2N R9W T4S R5W |
Decision Memo · Flaming Gorge Ranger District · updated 4/21/2025
Wyoming 530 near the Henry's Fork wetlands and ponds · Sweetwater, Wyoming
This project would involve a special use permit for the existing road across public land that accesses the Wirick private property.
Special use management
Decision
04/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Vernal Ranger District · updated 4/16/2025
Forest Service Road 52 runs along the south ridge of Dutch Charles Draw. · Uintah, Utah
The project would realign Forest Road (FR) 52 so that it branches off of FR 50, directly south of the Barker Spring Loop cattleguard. We would also replace the associated Little Brush Creek gate with fencing.
Grazing managementRoad management
Decision
04/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (24), 36 Cfr 220.6(E)(24) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Improvements/Construction; Grazing Structural Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 1/23/2025
Little Hole Day Use Area, Ramp #3 · Daggett, Utah
We would install a j-hook rock structure above Little Hole Ramp #3 to protect the ramp from scouring and erosion during high flows.
Facility management
Scoping Start
02/2025 (Estimated)
Decision
03/2025 (Estimated)
Implementation
04/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 12/20/2024
This is approximately 323 feet of access road across the Ashley National Forest to the Yellowstone Ranch private inholding. · Duchesne, Utah
This project would grant a right-of-way special use permit for an existing access road across National Forest System land to a private property inholding. There would be no change to the existing use of the road.
Special use management
Decision
12/2024 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 10/31/2024
Forest Service Road 144, North Fork Duchesne River, near Hanna, UT · Duchesne, Utah
This project would involve the installation and operation of approximately 5.1 miles of new fiber optic communications cables and ancillary facilities in non-continuous routes in the project area.
Special use management
Decision
10/2024 (Estimated)
Implementation
05/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T1N, R8W, Sec 19, 18, 7 and T2N, R8W, Sec 12, 1, 36, 35, 26, 23, 22 |
Decision Memo · Vernal Ranger District · updated 9/11/2024
Cart Creek Meadow area, approximately 20 miles north of Vernal, UT, adjacent to U.S. Highway 191 where Cart Creek crosses under the highway. · Daggett, Utah
Several restoration treatments would occur in a 244-acre project area, including canal reconstruction; lop and scatter; and seeding/planting. The project would increase wetlands, species diversity, and ecosystem resilience.
Watershed managementWildlife, fish, rare plants
Decision
07/2024 (Estimated)
Implementation
10/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 7/19/2024
2675 Cedar Springs Road, Dutch John, UT 84023 · Daggett, Utah
We would authorize the special use permittee to replace the modular home at the Cedar Springs Marina due to its deteriorating condition. The new home would meet modern standards for safety, functionality, and comfort.
Facility managementRecreation management
Decision
07/2024 (Estimated)
Implementation
08/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Maintenance |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Ashley National Forest All Units · updated 7/3/2024
All aspens stands on the Ashley National Forest outside of wilderness · Daggett; Duchesne; Summit; Uintah; Wasatch; Sweetwater, Utah; Wyoming
This is a programmatic evaluation of the restoration of aspen stands on the Ashley NF outside of Wilderness.
Wildlife, fish, rare plantsVegetation management (other than forest products)Fuels managementWatershed management
Comment Period
06/09/2021
Objection Period Start
06/08/2022
Decision
10/2023 (Estimated)
Implementation
10/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Salvage); Timber Sales (Green); Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Ashley National Forest All Units |
| Legal Land Description | All Ashley National Forest lands outside of wilderness |
Decision Memo · Flaming Gorge Ranger District · updated 6/24/2024
The trail construction would occur adjacent to the Lowline Trailhead parking lot near the Cedar Springs sewer lagoons in the Flaming Gorge National Recreation Area (NRA). · Daggett, Utah
Approximately 0.5 miles of new non-motorized trail construction to replace a section of the current Lowline Trail.
Recreation management
Decision
06/2024 (Estimated)
Implementation
08/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 5/30/2024
This project is located at the Dry Ridge Repeater Site. · Duchesne, Utah
This project would replace an existing communications shelter that currently does not meet design standards. The proposed new shelter would provide a safer environment for the electronic equipment.
Facility management
Decision
05/2024 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 5/30/2024
The Moon Lake recreation complex is in the Lake Fork drainage next to Moon Lake. The well would be constructed close to the Moon Lake parking area. · Duchesne, Utah
We are proposing a well at the Moon Lake recreation complex to replace two groundwater spring systems that were wiped out after debris flows and landslides in 2023. The well would supply water to the Moon Lake Lodge, Moon Lake CG, and range troughs.
Recreation management
Decision
05/2024 (Estimated)
Implementation
06/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 5/21/2024
Government Park Meadow, north of Vernal, UT by approximately 27 miles, adjacent to the Red Cloud Loop · Uintah, Utah
The Ashley National Forest proposes to install hand-built structures and check dams to restore a degraded stream and meadow within Government Park.
Vegetation management (other than forest products)Watershed management
Decision
05/2024 (Estimated)
Implementation
09/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Duchesne Ranger District · updated 5/20/2024
The project area is at the Brown Duck Creek crossing on the Lake Fork Trail where the creek enters Moon Lake. · Duchesne, Utah
The project would involve relocation of flood debris to restore a safe stream crossing for users of the Lake Fork and Brown Duck Basin trails.
Recreation management
Decision
05/2024 (Estimated)
Implementation
06/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (19), 36 Cfr 220.6(E)(19) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 5/20/2024
Yellowstone, Bridge, Rock Creek, Upper Stillwater, Aspen, Avintaquin, and Iron Mine recreation sites and the Uinta Guard Station administrative site · Duchesne, Utah
To improve visitor services, vault toilet replacements or upgrades would occur at eight sites on the Duchesne-Roosevelt Ranger District.
Recreation management
Decision
05/2024 (Estimated)
Implementation
06/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21); 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District; Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Duchesne Ranger District · updated 5/13/2024
The project area is within and adjacent to an existing road quarry, less than 1 mile north of Mill Park, in the Hells Canyon area of the Ashley National Forest. · Duchesne, Utah
This is a proposal for small-scale locatable minerals exploration and sampling, within and immediately adjacent to an existing Forest Service rock quarry near Mill Park. Expected disturbance would be less than 0.1 acres.
Minerals and geology
Decision
05/2024 (Estimated)
Implementation
07/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Duchesne Ranger District · updated 5/13/2024
The Yellowstone ATV trail is located on the Ashley National Forest in the Yellowstone Canyon/ Petty Mountain area. · Duchesne, Utah
The Yellowstone ATV Trail connections are currently 50 inches wide and off-highway vehicles (OHVs) greater than 50 inches are prohibited. By reconstructing the trail to 60 inches, the Yellowstone ATV Trail would be accessible to more forest visitors.
Recreation management
Decision
05/2024 (Estimated)
Implementation
06/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 5/7/2024
This project is located immediately west of Moon Lake Campground. · Duchesne, Utah
We would construct a gabion berm as well as riprap drainage channel slopes to mitigate debris flow hazards to the Moon Lake Campground and Moon Lake Guard Station.
Recreation management
Decision
05/2024 (Estimated)
Implementation
05/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3); 32.12 (5), 36 Cfr 220.6(D)(5); 32.2 (19), 36 Cfr 220.6(E)(19) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Duchesne Ranger District · updated 5/6/2024
Headwaters of Iron Mine Creek, on the north side of the creek. · Duchesne, Utah
Proposal to construct approximately 1 mile of new access road, across the Ashley NF and UWC NF, and then begin small-scale hardrock mining operations for decorative calcite on the Ashley NF, near the headwaters of Iron Mine Creek.
Minerals and geology
Comment Period
10/11/2023
Objection Period Start
02/28/2024
Decision
05/2024 (Estimated)
Implementation
06/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Ashley National Forest; Uinta-Wasatch-Cache National Forest |
| Districts | Duchesne Ranger District; Heber-Kamas Ranger District |
| Legal Land Description | T2N R9W Sec 19 of Uintah Meridian, and T3N R9E Sec 18 of Salt Lake Meridian. |
Decision Memo · Vernal Ranger District · updated 4/19/2024
The project would include areas throughout the Cart Creek Watershed. This area includes areas west and east of Highway 191 and the Limber Flag Yurt area east of Potholes. · Daggett; Uintah, Utah
This project would establish a 760-acre linear fuel break, primarily along Highway 191 and the Limber Flag Yurt Road, to protect watersheds in the area from negative impacts from a large wildland fire event.
Fuels management
Decision
04/2024 (Estimated)
Implementation
07/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3(11) |
| Special Authority | 2021 Infrastructure: Fuel Break Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District; Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Duchesne Ranger District · updated 4/18/2024
The proposed connector trail is in the Pole Mountain area east of Uinta Canyon and would connect Forest Service Roads (FSRs) 289 and 290. · Duchesne, Utah
This project would involve construction of a new portion of motorized trail connecting with existing roads open to all-terrain vehicle (ATV) use to create a loop trail along the Elkhorn Loop Road.
Recreation management
Decision
04/2024 (Estimated)
Implementation
06/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 3/26/2024
Whiterocks, Oaks Park, Kaler Hollow, Range Study, Beaver Pond, and Red Springs on D2 and Moose Pond, Dowd Mountain, Sheep Creek Bay, Navajo Cliffs, Palisades, Antelope Flat, and Ute Mountain on D1 · Daggett; Uintah, Utah
To improve visitor services, vault toilet replacements would occur at six recreation sites on the Vernal Ranger District (D2) and seven recreation sites on the Flaming Gorge Ranger District (D1).
Facility managementRecreation management
Decision
03/2024 (Estimated)
Implementation
06/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District; Vernal Ranger District |
| Legal Land Description | Not Applicable |
Environmental Impact Statement · Ashley National Forest All Units · updated 2/8/2024
This project involves the entire Ashley National Forest. · Daggett; Duchesne; Summit; Uintah, Utah
The Ashley National Forest completed revision of its 1986 Forest Plan to reflect current natural resource conditions. We released the final revised Forest Plan on 1/26/2024.
Land management planning
NOI in Federal Register
09/10/2019
DEIS NOA in Federal Register
11/19/2021
FEIS NOA in Federal Register
01/26/2024
Objection Period Start
04/19/2023
Decision
01/2024 (Estimated)
Implementation
02/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Plan Creation/Revision |
| Forests | Ashley National Forest |
| Districts | Ashley National Forest All Units |
| Legal Land Description | Not Applicable |
Environmental Assessment · Ashley National Forest All Units · updated 11/9/2023
Approximately 4 miles northeast of Manila, Utah near the intersection of Highway 530 and Forest Road 146 (Lucerne Road). · Sweetwater, Wyoming
This project would involve the development of a recreation and interpretive site to provide for public education, enjoyment, and protection of the Henry's Fork prehistoric rock art site.
Recreation managementHeritage resource management
Comment Period
09/24/2022
Objection Period Start
08/30/2023
Decision
11/2023 (Estimated)
Implementation
11/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Dispersed Recreation Mgmt.; Heritage Resource Management; Trail Management; Road Improvements/Construction |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 10/12/2023
The pre-commercial thinning units are located throughout the Ashley Karst National Recreation and Geologic Area north of Vernal, Utah. · Uintah, Utah
We would thin approximately 7,571 acres of young lodgepole pine stands to improve forest health, reduce the risk of undesirable wildfires, and enhance wildlife habitat.
Vegetation management (other than forest products)
Decision
10/2023 (Estimated)
Implementation
07/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Vernal Ranger District · updated 9/26/2023
The project area includes the Marsh Peak, Lakeshore Basin, Lake Mountain, and Black Canyon Allotments on the south slope of the Uinta Mountains in the Vernal Ranger District. · Uintah, Utah
We are proposing to adjust the boundaries of the closed Marsh Peak Allotment to facilitate and improve livestock management on the neighboring Lake Mountain and Black Canyon Allotments.
Grazing management
Comment Period
04/19/2023
Objection Period Start
08/02/2023
Decision
09/2023 (Estimated)
Implementation
12/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Allotment Management |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Duchesne Ranger District · updated 6/29/2023
This project would occur in the Strawberry Watershed in Duchesne and Wasatch Counties. Approximately 37,783 acres of the 60-783-acre project would occur on lands managed by the Ashley National Forest. · Duchesne; Wasatch, Utah
This project would mitigate ongoing impacts from the 2018 Dollar Ridge Fire by repairing or improving conditions on fire-impacted lands to put them on a trajectory for a quicker natural recovery.
Watershed management
Comment Period
02/15/2023
Objection Period Start
05/03/2023
Decision
06/2023 (Estimated)
Implementation
07/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 6/6/2023
The project area includes the Red Cloud Loop Road, Horseshoe Park, Massey Cave, and Marsh Bench Road. · Uintah, Utah
This would be an approximately 2,900-acre fuels reduction project, mostly along the Red Cloud Loop Road. Vegetation treatments would include mastication, mowing, slashing, and piling and burning, as well as falling trees for firewood collection.
Fuels management
Decision
06/2023 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3(11) |
| Special Authority | 2021 Infrastructure: Fuel Break Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 5/30/2023
Red Canyon Lodge Resort is about 14 miles southwest of Dutch John, Utah off of Highway 44. · Daggett, Utah
We would authorize the special use permittee to remove old shower houses, mobile homes, and cabins and and install new facilities. New facilities would include a shower house, seasonal bunkhouses, storage buildings, and RV pads.
Special use management
Decision
05/2023 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Secs. 27, 34 T. 2 N, R. 21 E., Salt Lake principal meridian |
Decision Memo · Flaming Gorge Ranger District · updated 5/30/2023
The project area is the Stateline Cove Campground, which is approximately 6 miles ENE of Manila, UT. · Daggett, Utah
The campground concessionaire and the Forest Service would construct a drivable path from the campground to the water area and install a new loading dock in the water.
Special use management
Decision
05/2023 (Estimated)
Implementation
07/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 5/23/2023
The Lucerne Valley Marina boat launch is approximately 9 miles east of Manila, UT. · Daggett, Utah
We would authorize the UDWR to install a 10,000-gallon dip tank at the Lucerne Valley Marina adjacent to the boat launch. Hot water in the dip tank would sanitize boats with aquatic invasive species, such as zebra and quagga mussels.
Special use management
Decision
05/2023 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Sec. 20, T. 3 N. R. 21 E., Salt Lake principal meridian |
Decision Memo · Vernal Ranger District · updated 2/21/2023
This project would involve two sections of the Outline Trail on the Vernal Ranger District. · Uintah, Utah
We are proposing to reroute two approximately 800-foot very steep sections of the Outlaw Trail to address safety, resource, and social concerns.
Recreation management
Decision
02/2023 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Vernal Ranger District · updated 1/26/2023
The general location is in Round Park off of Forest Service Road (FSR) 020. The stream is adjacent to FSR 547. · Uintah, Utah
This project would involve placement of grade control structures in Dyer Creek to halt head cutting and erosion.
Watershed management
Decision
01/2023 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Vernal Ranger District · updated 1/19/2023
The project area is on Forest Service Trail (FST) 011 (Little Brush Creek 2 Trail) and FST 208 (Little Brush Creek to Cutoff Trail) on the Vernal Ranger District. · Uintah, Utah
We are proposing to re-designate portions of the Little Brush Creek 2 and Little Brush Creek to Cutoff off-highway vehicle (OHV) Trails from 50 inches to 60 inches.
Recreation management
Decision
01/2023 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Duchesne Ranger District · updated 12/1/2022
Near US Highway 191 in Indian Canyon · Duchesne, Utah
The Seven County Infrastructure Coalition is constructing 11 borings to provide relevant geotechnical data to advance design of the Uinta Basin Railway Project. This CE is just for the borings.
Special use management
Decision
11/2022 (Estimated)
Implementation
12/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Duchesne Ranger District · updated 11/22/2022
20 miles north of Mountain Home, UT · Duchesne, Utah
Duchesne County has received funding from the Natural Resources Conservation Service (NRCS) to conduct measures necessary to stabilize drainages, reduce erosion, improve water quality, and maintain vehicle access in the East Fork Fire area.
Watershed management
Decision
11/2022 (Estimated)
Implementation
11/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7); 32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (19), 36 Cfr 220.6(E)(19); 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Ashley National Forest All Units · updated 9/19/2022
The project area is northwest of Vernal, Utah, along the southern slopes of the Uinta Mountains within Uintah County. · Uintah, Utah
There is no longer a need for an EA, since no site-specific actions are involved. We are continuing preparation of a management plan for the Ashley Karst National Recreation & Geologic Area. See draft plan at: https://www.fs.usda.gov/ashley.
Special area managementLand management planningRecreation managementMinerals and geologyWatershed management
Decision
08/2022 (Estimated)
Implementation
08/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Dispersed Recreation Mgmt.; Plan Amendment; Roadless Area Management; Special Area Management; Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Duchesne Ranger District · updated 9/16/2022
Uinta Canyon near southern Forest boundary along FSR 118 and at Smokey Springs near the Uinta Canyon Trailhead. Rock Creek Canyon near the southern Forest Boundary at Lower Stillwater Ponds. · Duchesne, Utah
The purpose of this project is to restore water control structures, improve fish habitat, and improve access opportunities at two fishponds in Uinta Canyon and several fishponds in the Lower Stillwater area of Rock Creek Canyon.
Wildlife, fish, rare plantsWatershed management
Decision
09/2022 (Estimated)
Implementation
09/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1); 32.2 (7), 36 Cfr 220.6(E)(7); 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 9/9/2022
The project area is adjacent to the Eagle Creek Ranch, which is approximately 11 miles from Dutch John, UT in the general vicinity of the Red Canyon Lodge area. · Daggett, Utah
Eagle Creek Ranch currently has a special use permit for a culinary water system on National Forest System lands. This project would involve authorizing them to replace their water tank and reconstruct their water system.
Special use management
Decision
07/2022 (Estimated)
Implementation
09/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 9/8/2022
The project area runs along roadways in the western portion of the Flaming Gorge Ranger District (west of State Highway 44 in Daggett and Summit Counties, UT). · Daggett; Summit, Utah
This project would involve cutting dwarf mistletoe infected trees along roadways to improve forest health. The project would also help reduce fire hazard and would provide additional firewood collection opportunities to the public.
Vegetation management (other than forest products)Forest products
Decision
09/2022 (Estimated)
Implementation
10/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 9/8/2022
Access to the proposed parking area is an existing administrative road to the Cedar Springs Sewer Lagoon. This area is in the southeast portion of the Flaming Gorge National Recreation Area. · Daggett, Utah
We are proposing to seasonally open an administrative use road and construct a trailhead. The purpose of the project is to offer safer parking for recreationists off of Highway 191.
Recreation management
Decision
08/2022 (Estimated)
Implementation
09/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (24), 36 Cfr 220.6(E)(24) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Dispersed Recreation Mgmt.; Trail Management; Travel Management |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Vernal Ranger District · updated 8/29/2022
We would move the gate from the East Park Turnoff approximately 1 mile to the NW up the Red Cloud Loop. · Uintah, Utah
We would relocate a gate approximately 1 mile to the northwest of its current location and improve a turn-around area at this site. This would provide a parking location with more reliable snow cover for over-snow winter activities.
Recreation management
Decision
08/2022 (Estimated)
Implementation
09/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (24), 36 Cfr 220.6(E)(24) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Dispersed Recreation Mgmt.; Travel Management |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Duchesne Ranger District · updated 8/19/2022
On multiple allotments across the Vernal and Roosevelt-Duchesne Ranger Districts. · Duchesne; Uintah, Utah
This project would involve the construction of various range improvements, including water systems, drift fences, and spring exclosures, to improve cattle distribution on the Vernal and Roosevelt-Duchesne Ranger Districts.
Grazing managementWatershed management
Comment Period
03/09/2022
Objection Period Start
06/01/2022
Decision
07/2022 (Estimated)
Implementation
08/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Allotment Management; Grazing Structural Improvements; Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District; Roosevelt Ranger District; Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Ashley National Forest All Units · updated 8/15/2022
The cable would be buried along State Highway 530 and Forest Service Road 009 (Buckboard Crossing Road). Portions of the project are on the Flaming Gorge Ranger District in Wyoming. · Sweetwater, Wyoming
All West is seeking to install a fiber optic cable from Green River, WY to the Buckboard Marina and Campground. Approximately 3 miles of the 24-mile project would occur on the Ashley National Forest.
Special use management
Comment Period
03/16/2022
Objection Period Start
06/22/2022
Decision
08/2022 (Estimated)
Implementation
08/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Nepa Document Prepared By Another Federal Agency |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | T. 16 N., R. 108 W., sections 8, 17, & 18; and T. 15 N., R. 108 W., sections 28, 29, & 30, Sixth Principal Meridian, WY |
Decision Memo · Flaming Gorge Ranger District · updated 7/29/2022
Town of Dutch John · Daggett, Utah
The Town of Dutch John has requested a right-of-way special use permit for the road located on the east side of the Forest Service yard in Dutch John, UT. The town would widen the current road by about 50 feet and lengthen it about 150 feet.
Special use managementRoad management
Decision
07/2022 (Estimated)
Implementation
09/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Road Improvements/Construction |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Duchesne Ranger District · updated 7/27/2022
Reservation Ridge, Forest Road 147 · Duchesne, Utah
The applicant has requested access to their private property on Reservation Ridge in the winter with a highway legal vehicle. The Forest Service holds the road right-of-way in this location, so the proponent would need to obtain a special use permit.
Road management
Decision
09/2022 (Estimated)
Implementation
11/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Travel Management |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T. 11S., R. 10 E., 26 Sec. 11,12 |
Decision Memo · Roosevelt Ranger District · updated 7/12/2022
We would build turnouts along a 4-mile segment of the Hells Canyon Road (Forest Service Road [FSR] #227)from the Hells Canyon Bridge to the junction of the Petty Creek - Hells Canyon Road (FSR #196). · Duchesne, Utah
We are proposing to build intervisible pullouts along the Hells Canyon Road by widening the road in select locations. This would allow vehicles to pull over and pass each other safely on this narrow road.
Road management
Decision
07/2022 (Estimated)
Implementation
07/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (23), 36 Cfr 220.6(E)(23) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Roosevelt Ranger District · updated 7/1/2022
12 miles North of Mountain Home · Duchesne, Utah
Replacement of the Hells Canyon Creek Bridge would involve removal of the bridge and the wooden abutments. New concrete footings would be installed within the existing roadbed but farther away from the stream.
Road management
Decision
06/2022 (Estimated)
Implementation
08/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | 2N 4W Sec 17 |
Decision Memo · Roosevelt Ranger District · updated 6/29/2022
Within footprint of existing USFS road quarry near Mill Park, in the Hells Canyon area of the Ashley National Forest. · Duchesne, Utah
Small-scale mineral exploration. Trenching and sampling for valuable minerals, within disturbance footprint of existing Forest Service rock quarry near Mill Park in Hells Canyon area. Less than 10 days work. Disturbance less than 0.1 acres.
Minerals and geology
Decision
06/2022 (Estimated)
Implementation
07/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | T2N R5W Sec 3-4 |
Decision Memo · Duchesne Ranger District · updated 6/29/2022
South Fork Rock Creek Road Near Arda Lake Turn · Duchesne, Utah
Replacement of the South Fork Rock Creek Bridge would involve removal of the bridge and the wooden abutments. New concrete footings would be installed within the existing road bed but farther away from the stream.
Road management
Decision
06/2022 (Estimated)
Implementation
08/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | 2N 6W Sec 19 |
Decision Memo · Roosevelt Ranger District · updated 6/13/2022
The borrow site is in Yellowstone Canyon near Riverview Campground. · Duchesne, Utah
We would expand an existing Forest Service borrow site used for road maintenance surfacing and fill material for all the roads in the Yellowstone Canyon area. The current size of the borrow site is 1/2 acre. We would expand the site to be 1 acre.
Road management
Decision
06/2022 (Estimated)
Implementation
07/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21); 32.2 (23), 36 Cfr 220.6(E)(23) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Ashley National Forest All Units · updated 6/2/2022
Approximately 25 miles north of Vernal along Hwy 191 and numerous side roads off of 191, including in the Bowden and Greens draws, Bassett Springs, Grizzly Hollow and Ridge, and Francis Creek areas. · Daggett; Uintah, Utah
This is a proposed timber and forest health project that includes aspects of fuels reduction, public safety, and aspen restoration. The project area is within a Utah Shared Stewardship priority landscape area.
Fuels managementForest productsWatershed managementVegetation management (other than forest products)
Comment Period
11/03/2021
Objection Period Start
03/23/2022
Decision
06/2022 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green); Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District; Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Vernal Ranger District · updated 3/14/2022
The general location is in Round Park off of FS Road 020. The stream is adjacent to FS Road 547. · Daggett, Utah
This project would involve the placement of grade control structures in Dyer Creek to halt head cutting and erosion.
Watershed management
Decision
03/2022 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | T1S R21E Sec 2 and 3 |
Decision Memo · Duchesne Ranger District · updated 3/11/2022
Ashley NF-South Unit, .03 miles east of HWY 191 and .03 miles north of Argyle Canyon rd. · Duchesne, Utah
The Forest Service would designate a less than 1 acre site for community members to drop off vegetation removed from their property one to two times a year. The material would then be piled using machinery and burned when there is snow on the ground.
Special use managementFuels management
Decision
03/2022 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Township 7 South Range 8 West Section 12 |
Decision Memo · Duchesne Ranger District · updated 3/7/2022
Guzzlers would be located on Raspberry Ridge and Draw (southeast of Moon Lake), Dry Ridge (ridge west of Moon Lake), and Cow Hollow (Timber Canyon area of the South Unit). · Duchesne, Utah
Two wildlife guzzlers were burned over during wildfires. The proposal is to replace these two wildlife guzzlers and install five new guzzlers for wildlife benefit and use.
Wildlife, fish, rare plants
Decision
01/2022 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Hfra Title Iii: Watershed Forestry Assistance; Hfra Title Vi: Greater Sage-Grouse And Mule Deer Habitat Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | R112W, T2N, section 21; R111, T2N, Section 22; R9w, T4S, Sections 27&34 |
Decision Memo · Duchesne Ranger District · updated 1/18/2022
The admin site to be conveyed includes the historic old Stockmore ranger station (parcel 1) south of Highway 35 and some excess property located north of the highway east of the horse pasture. · Duchesne, Utah
The Roosevelt/Duchesne Ranger District of the Ashley National Forest proposes to convey portions of the Stockmore administrative site to GSA as excess property.
Facility managementHeritage resource management
Decision
01/2022 (Estimated)
Implementation
01/2022 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (7), 36 Cfr 220.6(D)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Land Exchanges |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Parcel 1-Township 1 North, Range 8 West, Section 19, SESE; Section 20, SWSW. Parcel 2 is located north of highway 35 and east of the admin site horse pasture fence. |
Decision Memo · Ashley National Forest All Units · updated 12/21/2021
Northeast of East Park reservoir located on Forest Service Road 10021 at the East Park Communication Site. · Daggett, Utah
The Ashley NF would issue a new 30-year special use permit to Utah Communications Authority for existing infrastructure at the East Park communications site. The new permit would replace the existing permit issued to the State of Utah.
Special use management
Decision
12/2021 (Estimated)
Implementation
12/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | SW1/4N/W1/4N/W1/4OF sec, 12 T.1N.,R.21E, Salt Lake Meridian Utah |
Decision Memo · Ashley National Forest All Units · updated 12/20/2021
Dutch John Gap which is approximately 3 miles west northwest of the community of Dutch John, Utah. The project can be accessed from Highway 191 and Forest Service Road 012. · Daggett, Utah
The Ashley NF would issue a new 30-year special use permit to Union Wireless for an existing cell phone tower and related infrastructure at Dutch John Gap. The permit would replace the existing special use permit and consolidate amendments.
Special use management
Decision
12/2021 (Estimated)
Implementation
12/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 11/2/2021
Dutch John, Utah · Daggett, Utah
Marina facility additions
Special use management
Decision
11/2021 (Estimated)
Implementation
11/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Sec. 16, T. 2 N., R. 22 E., Salt Lake Meridian |
Decision Memo · Duchesne Ranger District · updated 10/4/2021
The project is located within the Dry Ridge area, with both proposed drill-holes to be located in section 8 of T2N R6W, Uinta Meridian. · Duchesne, Utah
The proponent has submitted a plan of operations for exploratory drilling for locatable minerals in the Dry Ridge area of the Ashley NF. The plan includes drilling two holes, each up to 600 feet deep, within existing mining claims.
Minerals and geology
Decision
10/2021 (Estimated)
Implementation
10/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Roosevelt Ranger District · updated 9/30/2021
The trail segment is located approximately 1.1 miles from the Uinta Trailhead off Forest Service Road 118, about 2.5 miles south of the High Uintas Wilderness boundary. · Duchesne, Utah
A portion of the Uinta River Trail would be resurfaced with mineral soil from an adjacent borrow site to improve footing for pack stock.
Recreation management
Decision
07/2021 (Estimated)
Implementation
07/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Legal Location of Borrow Pit Site: SE 1/4 NW 1/4, Sec. 19, T3N R2W; Legal Location of North and South Terminus of Trail Segments: SE 1/4 NE 1/4, Sec. 24, T3N R3W; SE 1/4 NW 1/4, Sec.19 T3N R2W. |
Environmental Impact Statement · Roosevelt Ranger District · updated 9/20/2021
High Uintas Wilderness Area Roosevelt Ranger District, Duchesne Ranger District. · Duchesne, Utah
Cooperative project with UDWR to restore and enhance CRCT populations within the High Uintas wilderness through the use of piscicide rotenone to remove non-native fish from selected streams and lakes. CRCT would be reintroduced following treatment
Wildlife, fish, rare plants
NOI in Federal Register
07/06/2010
DEIS NOA in Federal Register
12/24/2013
FEIS NOA in Federal Register
07/23/2019
Objection Period Start
07/23/2019
Decision
01/2020 (Estimated)
Implementation
05/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Species Habitat Improvements; Species Population Enhancements |
| High Uintas Wilderness Colorado River Cutthroat Trout (CRCT) Habitat Enhancement. | Decision Signed Date: 01/13/2020 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 9/17/2021
East Fork Carter Creek just below Sheep Creek Canal · Daggett, Utah
Construction of fish barrier using on-site rock to prevent upstream movement of non-native fish into restored waters with native cutthroat trout.
Wildlife, fish, rare plants
Decision
09/2021 (Estimated)
Implementation
09/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 9/17/2021
Proposed Site: Below the Kokanee Salmon Viewing Bridge, at the Sheep Creek Nature Trail pull-out, immediately downstream of Highway 44, UTMs 607728.00 m E, 4531574.00 m N · Daggett, Utah
The proposed action is to allow the UDWR to add 8-10 cubic yards of suitable spawning substrate (1-inch diameter gravel) to Sheep Creek in the immediate vicinity of the proposed site. Gravel would be purchased and hauled by the UDWR.
Wildlife, fish, rare plants
Decision
06/2021 (Estimated)
Implementation
08/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Population Enhancements |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Duchesne Ranger District · updated 8/26/2021
The project is located within the Iron Mine Creek drainage, in section 20 of T2N R9W, Uinta Meridian. · Wasatch, Utah
The proponents have submitted a plan of operations for mineral exploration activities in the Iron Mine Creek area. The plan includes trenching, bulk sampling, and 0.59 miles of temporary road construction for heavy equipment access.
Minerals and geology
Comment Period
02/03/2021
Objection Period Start
06/30/2021
Decision
08/2021 (Estimated)
Implementation
08/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T2N R9W Sec 17, 20 (Uinta Meridian) |
Decision Memo · Ashley National Forest All Units · updated 8/19/2021
The project is located approximately one mile northwest of Highway 44 on the Sheep Creek Geological Loop Road (Forest Service Road 218). · Daggett, Utah
Special Use Permit to authorize a 150' x 30' right of way to access privately owned property.
Special use management
Decision
07/2021 (Estimated)
Implementation
07/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Ashley National Forest All Units · updated 6/30/2021
Approximately 1 mile south of Moon Lake along Forest Service Road (FSR) 10131 · Duchesne, Utah
250 acres of timber salvage and 762 acres of tree seedling planting approximately 1 mile south of Moon Lake. This area experienced uncharacteristic stand-replacement fire in ponderosa pine during the 2020 East Fork Fire.
Fuels managementWatershed managementForest products
Comment Period
03/03/2021
Objection Period Start
05/05/2021
Decision
06/2021 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage); Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 6/30/2021
Grizzly Ridge communications site. 22 miles north of Vernal Utah, ? mile west of 191. · Utah, Utah
T-Mobile would install a new 11' x 20' communications shelter adjacent to Strata Networks' recently constructed cell tower. T-Mobile would co-locate signal receiver dishes on the Strata Networks tower.
Special use management
Decision
06/2021 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Duchesne Ranger District · updated 6/25/2021
The fish migration barrier is located on the South Unit of the Duchesne District on Timber Creek near the northern Forest boundary. (T. 1 S., R. 112 W.) · Duchesne, Utah
The Timber Creek fish migration barrier has become less effective as a result of accumulated debris. This project would use a track hoe to remove the downed tree and debris upstream of the barrier to re-establish the effectiveness of the barrier.
Wildlife, fish, rare plants
Decision
06/2021 (Estimated)
Implementation
07/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7); 32.2 (11), 36 Cfr 220.6(E)(11) |
| Special Authority | National Fire Plan - Healthy Forests Initiative Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T. 1 S., R. 112 W. |
Decision Memo · Ashley National Forest All Units · updated 6/24/2021
The project is located adjacent to Grizzly Ridge and near the Deer Lodge summer home area. The project is accessed from the west side of Highway 191 between Vernal and Flaming Gorge off of FSR 056. · Uintah, Utah
The Forest Service plans to issue a Special Use Permit to Moon Lake Electric Company to replace 14 power poles and power lines that connect to the Grizzly Ridge communications site and to other residences in Daggett County, Utah.
Special use management
Decision
05/2021 (Estimated)
Implementation
07/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Forest Service Energy Implementation Plan |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 5/5/2021
West Northwest Region of the Flaming Gorge District in Utah and Wyoming. The project spans from the eastern to western edge of the district primarily south of Manila. · Daggett; Sweetwater, Utah; Wyoming
The project will remove conifer species from shrub community types through lop and scatter on 19,682 acres. The project intent is to maintain native vegetation diversity, watershed stability, reduce wildfire potential, and improve wildlife habitat.
Fuels managementVegetation management (other than forest products)Wildlife, fish, rare plants
Decision
05/2021 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Population Enhancements |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Duchesne Ranger District · updated 1/25/2021
On the western end of the Duchesne Ranger District, east of Wolf Creek Summit. Landmarks in the area include Little Pond, Left Fork Rhoades Canyon, and Mill Fork. · Duchesne; Wasatch, Utah
A timber and forest health project that includes aspects of public safety, watershed restoration, and fuels reduction.
Vegetation management (other than forest products)Fuels managementForest productsWatershed management
Comment Period
11/24/2020
Decision
01/2021 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green); Watershed Improvements |
| Little Pond Forest Restoration Project Final Decision Notice | Decision Signed Date: 01/04/2021 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 1/5/2021
The guzzler is located southeast of Moon Lake on the ridge dividing Raspberry Draw and Mackentire Draw on Petty Mountain of the Duchesne/Roosevelt Ranger District. · Duchesne, Utah
Replace an existing guzzler on Raspberry Ridge of the Duchesne/Roosevelt RD that has been damaged beyond repair.
Wildlife, fish, rare plants
Scoping Start
04/2021 (Estimated)
Decision
09/2021 (Estimated)
Implementation
09/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | The legal location of the project is T2N, R5W, Northeast quarter of the Southeast quarter of Section 21 |
Environmental Impact Statement · R2 - Rocky Mt. Region All Units · updated 12/10/2020
Linear transmission lines located in Colorado, Utah, and Nebraska · Dawes; Daggett; Uintah; Chaffee; Delta; Dolores; Eagle; Grand; Gunnison; Jackson; Lake; La Plata; Larimer; Mesa; Montrose; Routt; Saguache; San Juan, Colorado; Nebraska; Utah
Update vegetation management activities along 278 miles of transmission lines located on NFS lands in Colorado, Nebraska, and Utah. These activities are intended to protect the transmission lines by managing for stable, low growth vegetation.
Special use management
NOI in Federal Register
04/08/2010
DEIS NOA in Federal Register
09/27/2013
FEIS NOA in Federal Register
12/10/2020
Objection Period Start
08/10/2020
Decision
11/2020 (Estimated)
Implementation
12/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| WAPA Right-of-Way Maintenance and Reauthorization | Decision Signed Date: 11/17/2020 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests; Medicine Bow-Routt National Forest; Nebraska National Forest; Arapaho and Roosevelt National Forests; Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands; San Juan National Forest; White River National Forest; Ashley National Forest |
| Districts | Grand Valley Ranger District; Norwood Ranger District; Gunnison Ranger District; Paonia Ranger District; Yampa Ranger District; Hahns Peak/Bears Ears Ranger District; Pine Ridge Ranger District; Boulder Ranger District; Canyon Lakes Ranger District; Sulphur Ranger District; Salida Ranger District; Mancos/Dolores Ranger District; West Zone/Sopris Ranger District; East Zone/Dillon Ranger District; Ashley National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Vernal Ranger District · updated 9/16/2020
This project is located in Uintah County, north of Vernal, UT. The project area is located approximately between Iron Spring Campground and Taylor Mountain Road Forest Road 044. · Uintah, Utah
This project would reroute a popular section of a multi-use trail to provide an improved recreational experience and to improve resource conditions. An additional trail (<50")would be constructed from the current trail to a turn around near the cave.
Recreation management
Decision
07/2020 (Estimated)
Implementation
08/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1); 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Vernal Ranger District · updated 9/16/2020
The project is located along Highway 191, north of Vernal, Utah at the trailhead and ends at the intersection of North East Park Forest Road 212. · Daggett; Uintah, Utah
Rerouting and reconstructing a motorized section of the Highline Trail between Highway 191 and East Park Reservoir. The project purpose is to improve the visitor experience and minimize impacts such as erosion to the resources of the area.
Recreation management
Decision
07/2020 (Estimated)
Implementation
08/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Duchesne Ranger District · updated 9/4/2020
The project is located south of Highway 40 at the junction of Sowers Canyon Road and Forest Service Road 497, approximately 6.15 miles south of the Bridgeland turn off. · Duchesne, Utah
Construction of an OHV trail connection on the South Unit of the Duchesne/Roosevelt Ranger District. The segment would connect Sowers Canyon Road to Forest Service Road 497. This segment would be approximately 3.3 miles.
Recreation management
Decision
09/2020 (Estimated)
Implementation
09/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Duchesne Ranger District · updated 8/19/2020
At the head of Hells Canyon. Landmarks in the area include Mill Park, Center Park, and Long Park in the northern portion of the project area and Bear Park and Flea Flat in the southern portion. · Duchesne, Utah
A timber and forest health project that includes aspects of public safety, watershed restoration, and fuels reduction.
Forest productsFuels managementWatershed managementVegetation management (other than forest products)
Comment Period
03/10/2020
Objection Period Start
05/26/2020
Decision
08/2020 (Estimated)
Implementation
09/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green); Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Vernal Ranger District · updated 8/3/2020
The project is approximately 20 miles north of Vernal and 0.75 miles west of Hwy 191, accessed by Forest Road 056. · Uintah, Utah
Special use renewal of an existing cell tower facility that is specifically used for controlling an automated pipeline system for oil and gas transport.
Special use management
Decision
08/2020 (Estimated)
Implementation
08/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | NW 1/4 of Section 17, T. 1 S, R 22 E., Salt Lake Meridian |
Decision Memo · Ashley National Forest All Units · updated 7/21/2020
Grizzly Ridge communication site is located approximately 20 miles north of Vernal and about 0.75 mile east of Highway 191, accessed off of Forest Road 056. · Uintah, Utah
Strata Networks is constructing a new cell tower on Grizzly Ridge that is 120 feet tall. Site vegetation will be removed and a chain link fence installed at the site. The project area is approximately 0.5 acres in size with a footprint of 125'X90'.
Facility management
Decision
07/2020 (Estimated)
Implementation
07/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Strata Cell Tower Project | Decision Signed Date: 07/21/2020 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 7/20/2020
The project is located 14.5 miles southwest of Duchesne Utah. On the East Side of Forest Road 152 directly after crossing the Forest Boundary. · Duchesne, Utah
The proposed action would involve restoring the stream and subsequently the water table. The proposed action would include construction, reconstruction, and maintenance of new and existing rock grade control structures.
Watershed management
Decision
07/2020 (Estimated)
Implementation
07/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Sowers Creek Restoration Project | Decision Signed Date: 07/16/2020 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Uintah Special Meridian Township 9 S, Range 5 W Section 7 |
Decision Memo · Flaming Gorge Ranger District · updated 4/30/2020
Trail to start in Dutch John, Utah. Trail Passes through Dutch John Canyon to the North of town through current state gravel pit and abandoned gravel pit. · Daggett, Utah
Creation of ATV trail from Dutch John, UT to connect with existing road system on BLM land near Goslin Mountain via Dutch John Canyon
Recreation management
Decision
06/2020 (Estimated)
Implementation
06/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Dispersed Recreation Mgmt.; Trail Management; Travel Management |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | T.2 N., R. 22 E., Northeast corner of section 2 |
Decision Memo · Flaming Gorge Ranger District · updated 4/2/2020
Sections 28, 29, 32, and 33 of T15N R108W of the 5th PM, Sweetwater County, Wyoming · Sweetwater, Wyoming
Buckboard Marina is under a Special Use Authorization to operate and maintain the marina and facilities. The owner/operators of the marina have requested to add a restaurant, shower house, and 5 additional RV pads to their existing facilities.
Special use management
Decision
12/2019 (Estimated)
Implementation
12/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Ashley National Forest All Units · updated 3/30/2020
9 sites on the Flaming Gorge Ranger District and 3 sites on the Vernal Ranger District. Sites range from Sweetwater County WY, to Daggett and Uintah counties, UT. · Daggett; Uintah; Sweetwater, Utah; Wyoming
We are proposing to decommission 12 developed recreation sites on the Flaming Gorge-Vernal Ranger District. These sites were chosen because of their limited use by the public, outdated facilities, and/or aging infrastructure.
Facility managementRecreation management
Comment Period
06/2019 (Estimated)
Objection Period Start
09/2019 (Estimated)
Decision
11/2019 (Estimated)
Implementation
01/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Land Use Adjustments; Developed Site Management; Dispersed Recreation Mgmt.; Facility Maintenance; Scenery Management |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District; Vernal Ranger District |
| Legal Land Description | T14NR108WSEC34;T2NR18SEC14;T2N22ESEC29;T3NR21E;SEC28;T2NR21ESEC35;T1SR20ESEC12;T2NR21ESEC21;T1NR22ESEC20;T2NR20ESEC9;T1SR21ESEC30;T2NR19ESEC12;T3NR21ESEC19; |
Decision Memo · Duchesne Ranger District · updated 2/3/2020
The project is located on the west side of the South Unit of the Duchesne/Roosevelt Ranger District of the Ashley National Forest, approximately 20 miles southwest of Duchesne Utah. · Duchesne, Utah
Wildlife habitat improvement project targeting the removal of encroaching confifers (pinyon, juniper, and Douglas fir), located on the South Unit of the Ashley National Forest. Treatment would be done through mechanical means using chainsaws.
Wildlife, fish, rare plantsVegetation management (other than forest products)
Decision
02/2020 (Estimated)
Implementation
08/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 1/31/2020
Sections A & B of the Green River below Flaming Gorge Reservoir located approximately 5 miles from Dutch John Utah. Launch points of Little Hole and Spillway. · Daggett, Utah
Renewal of 7 River Outfitter and Guide and 1 Shuttle Special Use Authorizations for a new 10 year term.
Special use management
Decision
12/2019 (Estimated)
Implementation
01/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Duchesne Ranger District · updated 12/10/2019
The Amber Onyx Mine would be in the Blind Stream drainage of the Duchesne District of the Ashley NF. Alongside Forest System road 121, near the center of Section 28, T2N R8W, Uinta Meridian. · Duchesne, Utah
A proposal for small-scale open pit mining operation at the proposed Amber Onyx Mine. Large blocks of decorative calcite would be removed from the mine. Up to 2.5 acres active disturbance proposed. Disturbed areas not needed would be reclaimed.
Minerals and geology
Comment Period
02/09/2016
Objection Period Start
05/03/2016
Decision
06/2016 (Estimated)
Implementation
06/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Amber Onyx Mine Project | Decision Signed Date: 06/27/2016 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | New mine site, to be located near center of Section 28, T2N R8W, Uinta Meridian. |
Environmental Assessment · Ashley National Forest All Units · updated 12/10/2019
Ashley National Forest · Daggett; Duchesne; Summit; Uintah; Sweetwater, Utah; Wyoming
Continue to implement the Forest Noxious Weeds Management Program by reviewing the 1994 Forest Noxious Weeds Management EA, supplement the analysis and update the Decision Notice/ FONSI.
Vegetation management (other than forest products)
Comment Period
09/02/2010
Decision
01/2013 (Estimated)
Implementation
04/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Noxious Weed Treatments |
| Ashley National Forest Noxious Weeds Management Supplement | Decision Signed Date: 01/30/2013 Legal Notice Date: 02/06/2013 |
| Forests | Ashley National Forest |
| Districts | Ashley National Forest All Units |
| Legal Land Description | All lands administered by the Ashley National Forest |
Environmental Assessment · Ashley National Forest All Units · updated 12/10/2019
The project is located in the High Uintas Wilderness, southeast of Kings Peak on the Roosevelt Ranger District. Lake Atwood is located northeast of Duchesne,and southwest of Manila, UT. · Duchesne, Utah
This project would issue a two year temporary special use permit to allow repair to Atwood Dam and provide continued operation of the dam, which is located in the High Uintas Wilderness, pending the issuance of a Ditch Bill Easement.
Special use management
Comment Period
11/25/2014
Objection Period Start
02/03/2015
Decision
03/2015 (Estimated)
Implementation
05/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | E1/2 of Section 14, T4N, R4W, USM |
Decision Memo · Duchesne Ranger District · updated 12/10/2019
The project is located on the west side of the South Unit of the Duchesne/Roosevelt Ranger District of the Ashley National Forest, approximately 20 miles southwest of Duchesne Utah. · Duchesne, Utah
The purpose of this project is to improve and maintain the shrub and grass/forb communities, and provide important wildlife habitat by deterring the encroachment of conifers (pinyon, juniper, and Douglas fir.
Wildlife, fish, rare plantsVegetation management (other than forest products)
Decision
06/2018 (Estimated)
Implementation
07/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Rangeland Vegetation Improvements |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Vernal Ranger District · updated 12/10/2019
The area can be reached by traveling north of Vernal or south of Dutch John on U.S. Highway 191 and traveling north/north-west on Forest Road 020. · Uintah, Utah
This project would involve approximately 4,145 acres of pre-commercial thinning of young lodgepole pine trees.
Vegetation management (other than forest products)
Decision
08/2017 (Estimated)
Implementation
08/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 12/10/2019
The project analysis area lies approximately 30 miles north of Vernal, Utah in Daggett County. It is above the Flaming Gorge Reservoir above Red Canyon. · Daggett, Utah
This project would improve bighorn sheep forage and lambing habitat, including increasing sight distances to detect predators, in areas along Flaming Gorge Reservoir. A combination of lop and scatter and prescribed fire would be used.
Wildlife, fish, rare plants
Decision
01/2016 (Estimated)
Implementation
01/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Roosevelt Ranger District · updated 12/10/2019
The project is located on Big Springs Road which splits off of the Uintah Canyon Highway (Highway 121). · Duchesne, Utah
There are approximately 0.38 miles of unpaved road that would be paved with asphalt. The existing road width is about 18 feet. The proposed project would increase the road width to 22 feet and the total right of way would be 60 feet.
Special use managementRoad management
Decision
04/2014 (Estimated)
Implementation
06/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Improvements/Construction |
| Bureau of Indian Affairs Big Springs Road Paving Project | Decision Signed Date: 04/15/2014 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Township 2 North, Range 2 West, Section 4 |
Decision Memo · Vernal Ranger District · updated 12/10/2019
Selected locations in the Cart Creek Watershed, located on both the Vernal and Flaming Gorge Ranger Districts. · Daggett; Uintah, Utah
We are proposing pre-commercial thinning as well as removal of conifers from riparian areas and from sagebrush communities to: improve timber stands, reduce the risk of unacceptable wildfires, and restore riparian and sagebrush plant communities.
Wildlife, fish, rare plantsVegetation management (other than forest products)Fuels management
Comment Period
09/11/2013
Decision
01/2014 (Estimated)
Implementation
05/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements |
| Cart Creek Integrated Vegetation Restoration Project | Decision Signed Date: 01/10/2014 Legal Notice Date: 01/14/2014 |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District; Vernal Ranger District |
| Legal Land Description | T1N R21E sections 11-14 and 23-26; T1N R22E sections 5-6, 8, 17, 20, & 29-32; T1S R22E sections 4-8; and T2N R22E sections 15-16, 21-22, 26-28, and 35 |
Decision Memo · Flaming Gorge Ranger District · updated 12/10/2019
Cedar Springs Marina, Flaming Gorge Reservoir · Daggett, Utah
Amendment of an existing special use authorization for Moon Lake Electric to add a new overhead 14.4/24.9 kV distribution line to serve the RV and boat storage area of the Cedar Springs Marina.
Special use management
Decision
02/2019 (Estimated)
Implementation
04/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 12/10/2019
Dutch John Mountain · Daggett, Utah
Amendment of an existing special use authorization for AT&T to add a new monopole and antennas to an existing communications site on Dutch John Mountain.
Special use management
Decision
02/2019 (Estimated)
Implementation
04/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Flaming Gorge Ranger District · updated 12/10/2019
Flaming Gorge Ranger District, including portions of the Flaming Gorge National Recreation Area, STATE – Utah, · Daggett, Utah
Maintain or move ponderosa pine vegetation types to a condition similar to historical conditions and improve the visual quality of key areas. Primary tool to accomplish this would be continuing or initial low intensity/high frequency fire.
Recreation managementWildlife, fish, rare plantsVegetation management (other than forest products)Fuels management
Comment Period
04/18/2012
Decision
05/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Scenery Management; Timber Sales (Salvage) |
| Flaming Gorge R.D. Ponderosa Pine Maintenance and Fuels Reduction Project | Decision Signed Date: 05/08/2013 Legal Notice Date: 05/15/2013 |
| Flaming Gorge Ranger District Ponderosa Pine Maintenance and Fuels Reductio | Decision Signed Date: 05/08/2013 Legal Notice Date: 05/15/2013 |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Portions of T2N, R19E - 23E and T1N, R19E - 21E, SLM |
Decision Memo · Ashley National Forest All Units · updated 12/10/2019
All system roads on the Ashley National Forest outside of the wilderness and natural resource areas. · Daggett; Duchesne; Uintah; Wasatch, Utah; Wyoming
Project to treat hazard trees along all system roads on the Ashley National Forest.
Forest productsVegetation management (other than forest products)Road management
Decision
05/2019 (Estimated)
Implementation
07/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Road Maintenance |
| Forests | Ashley National Forest |
| Districts | Ashley National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Vernal Ranger District · updated 12/10/2019
Various locations on the Flaming Gorge/Vernal RD and Flaming Gorge NRA. · Daggett; Uintah, Utah
Hand treatments (lop and scatter)on approximately 7,000 acres and mechanical treatments (mastication) on about 1,000 acres of conifer encroachment into Greater-sage grouse habitat.
Wildlife, fish, rare plants
Decision
07/2017 (Estimated)
Implementation
07/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Flaming Gorge Ranger District · updated 12/10/2019
The project is located in the vicinity of Half Moon Park, Whiskey Creek, and the historic Ute Lookout Tower on the Flaming Gorge Ranger District of the Ashley National Forest. · Daggett, Utah
This project would include a variety of timber and fuels vegetative management activities totaling 1,113 acres within a 1,787-acre project area. Trees killed by beetles or infected by dwarf mistletoe would be removed to achieve project objectives.
Wildlife, fish, rare plantsForest productsFuels managementWatershed management
Comment Period
01/31/2017
Objection Period Start
05/02/2017
Decision
08/2017 (Estimated)
Implementation
09/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green); Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Vernal Ranger District · updated 12/10/2019
The project is located about 20 miles north of Vernal, Utah on Highway 191, and about one mile north of Red Springs campground on the west side of the road. · Daggett, Utah
This project would involve building a short administrative road for the Forest to access barrier rock to be used in a variety of projects.
Minerals and geology
Comment Period
06/21/2016
Objection Period Start
08/23/2016
Decision
10/2016 (Estimated)
Implementation
10/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Road Maintenance; Travel Management; Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | SW ¼ of the NW ¼ of Section 17, T 1 N, R 22 E, Salt Lake Base Meridian |
Environmental Assessment · Vernal Ranger District · updated 12/10/2019
The project is located approximately 18 miles north northwest of Lapoint, Utah and can be reached by traveling up Mosby Mountain on Forest Road Number 10104. · Uintah, Utah
The project includes removing some down and dead trees to capture the economic value of these trees and to reduce hazardous fuel loading, as well as manipulation of live tree species composition, stand density, and stand structures.
Forest productsVegetation management (other than forest products)Fuels management
Comment Period
04/17/2013
Decision
05/2013 (Estimated)
Implementation
09/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green) |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Uintah Meridian, Township 3 North, Range 1 East, all or portions of sections 7, 8, 17, 18, 20, 28, and 29. Salt Lake Meridian, Township 2 South, Range 18 East, portions of sections 3, 4, 9, 10, 15, 1 |
Decision Memo · Vernal Ranger District · updated 12/10/2019
The project area lies mostly in the vicinity of the junction of the Elkhorn Loop and Chepeta Lake roads, as well as along the West Fork Trailhead Road. · Duchesne, Utah
This project would involve the removal of dead and dying hazard trees from along roadways and around developed sites in the vicinity of the junction of the Elkhorn Loop and Chepeta Lake roads.
Recreation managementForest productsFuels management
Comment Period
09/18/2013
Decision
02/2014 (Estimated)
Implementation
06/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Developed Site Management; Fuel Treatments (Non-Activity Fuels); Dispersed Recreation Mgmt.; Trail Management; Road Maintenance; Timber Sales (Salvage) |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District; Roosevelt Ranger District |
| Legal Land Description | T3N R1W, sections 6, 7, and 18; T3N R2W, sections 1 and 12; T4N R1W, sections 19, 30, and 31; and T4N R2W, sections 24 and 25; all Uintah Meridian |
Environmental Assessment · Ashley National Forest All Units · updated 12/10/2019
Project located in the Lake Fork drainage of the Roosevelt/Duchesne RD of the Ashley NF. · Duchesne, Utah
The purpose of this project is to reduce fuels in several vegetative communities, to provide additional protection to values at risk in the Lake Fork Drainage, and to improve wildlife habitat and ecological conditions.
Wildlife, fish, rare plantsVegetation management (other than forest products)Fuels management
Comment Period
03/20/2018
Objection Period Start
04/24/2018
Decision
06/2018 (Estimated)
Implementation
08/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Rangeland Vegetation Improvements |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Ashley National Forest All Units · updated 12/10/2019
The project is located approximately 40 miles northeast of Vernal, Utah and can be accessed by permission from the land owner using Highway 191, the Diamond Mountain Road, the Davenport Road and the Lambson Draw Road · Uintah, Utah
The Vernal-Flaming Gorge Ranger District proposes to convert the Lambson Draw On/Off Allotment from sheep use to cattle and horse use on the Ashley National Forest.
Grazing management
Comment Period
02/28/2017
Decision
04/2017 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Allotment Management |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Salt Lake Meridian, Township 1 North, Range 23 East, and portions of sections 3, 4, 9, 10, 11, 15, 16. |
Decision Memo · Duchesne Ranger District · updated 12/10/2019
Lower Stillwater ponds located in the Rock Creek drainage near the southern Forest boundary on the Duchesne District of the Ashley National Forest. · Duchesne, Utah
This project would enhance conditions for the fishery at the Lower Stillwater pond complex by dredging ponds to increase water depth, stabilizing banks and dykes, and improving water delivery.
Recreation managementWildlife, fish, rare plantsFacility management
Decision
09/2014 (Estimated)
Implementation
10/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Species Habitat Improvements; Facility Maintenance; Species Population Enhancements |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T.1 N. R.111 W. Sections 5 & 8 - Uinta Meridian |
Environmental Assessment · Duchesne Ranger District · updated 12/10/2019
Milk Lake is located in the High Uintas Wilderness on the Roosevelt Ranger District, within the Ashley National Forest. The Lake is located on the west side of the Yellowstone River Drainage. · Duchesne, Utah
Milk Lake dam has been in a deteriorated state and under a breach order since 1994. The Forest Service is proposing to modify the Milk Lake dam so that it no longer creates a hazard to the public and downstream resources.
Heritage resource managementWatershed managementFacility management
Comment Period
08/15/2017
Decision
09/2017 (Estimated)
Implementation
11/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Heritage Resource Management; Watershed Improvements; Wilderness Management |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T4N R5W Section 25 USM, within Duchesne County, Utah. |
Decision Memo · Vernal Ranger District · updated 12/10/2019
T1S R20E Sec.9 · Uintah, Utah
The proposed action for this project is to implement a fisheries habitat enhancement project in North Fork Ashley Creek, thereby increasing the pool and fisheries habitat. This would be accomplished by building large woody debris (LWD) structures.
Wildlife, fish, rare plants
Decision
04/2019 (Estimated)
Implementation
07/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | T1S R20E Sec9 |
Decision Memo · Ashley National Forest All Units · updated 12/10/2019
Yellowstone Canyon (powerline, telephone line, and a spring development/waterline); Uinta Canyon (powerline and hydroelectric); Moon Lake Canyon (powerline); and Sowers Canyon (powerline). · Duchesne, Utah
Renew SUPs for: 1.Yellowstone Cyn Powerline - MLEA 2.Cow Canyon Springs/Waterline - DCUCWID 3.Yellowstone Telephone Line - UBTA 4.Uinta Cyn Powerline - MLEA 5.Uinta Cyn FERC - MLEA 6.Moon Lake Powerline - MLEA 7.Sowers Cyn Powerline - Pacificor
Special use management
Comment Period
04/03/2013
Decision
08/2013 (Estimated)
Implementation
10/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Renewal of Special Use Permits, Roosevelt Duchesne Ranger District | Decision Signed Date: 08/30/2013 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District; Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Duchesne Ranger District · updated 12/10/2019
The South Fork Rock Creek and Blind Stream roadways as well as other system roads in the area. · Duchesne, Utah
Hazard tree removal within 300 feet of Forest Service Road (FSR) 143 (South Fork Rock Creek Road) and FSR 135 (Blind Stream Road), as well as FSRs 652, 649, and 140.
Recreation managementForest productsFuels managementRoad management
Decision
06/2018 (Estimated)
Implementation
07/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Dispersed Recreation Mgmt.; Road Maintenance; Timber Sales (Salvage); Timber Sales (Green) |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T1N R8W, sections 3, 10-11, and 14-15; T2N R7W, sections 19-20 and 30; T2N R8W, sections 14-15, 23-26, 28-29, and 33-36. |
Decision Memo · Vernal Ranger District · updated 12/10/2019
Uinta Mountains northwest of Vernal, Utah on the Flaming Gorge-Vernal Ranger District within Uintah County. · Uintah, Utah
Cheatgrass and other annual weed treatments, including drill seeding, broadcast seeding, and experimental burn.
Grazing managementVegetation management (other than forest products)
Decision
03/2019 (Estimated)
Implementation
07/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Noxious Weed Treatments |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Uintah Meridian Township 2N, Range 1E, Sections 20, 21; Salt Lake Meridian Township 3S, Range 18E, Sections 11, 13, 14, 15, 24 |
Decision Memo · Ashley National Forest All Units · updated 12/10/2019
Lake Fork Canyon is located on the Roosevelt-Duchesne Ranger District of the Ashley National Forest, within Duchesne County, Utah. · Duchesne, Utah
Issuance of a road use permit on an existing non-system road which provides access to private property located in Lake Fork Canyon. This existing non-system road will cross Lake Fork River and have a ROW of 2,510 feet long X 14 feet wide.
Special use management
Decision
10/2018 (Estimated)
Implementation
10/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | W1/2 of the NW1/4 of Sec. 34, T.2.N., R.5.W., U.S.M. |
Environmental Assessment · Flaming Gorge Ranger District · updated 12/10/2019
The project area is located approximately 13 miles southwest of Manila, Utah along Forest Service Road 001 between Hickerson Park and Spirit Lake. · Daggett, Utah
Commercial timber harvest as well as non-commercial vegetation management across 665 acres of heavy mountain pine beetle caused mortality and lodgepole pine dwarf mistletoe infection.
Forest productsVegetation management (other than forest products)Fuels management
Comment Period
04/25/2017
Objection Period Start
08/01/2017
Decision
10/2017 (Estimated)
Implementation
10/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green) |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | All Salt Lake Meridian: T1N, R17E, all or portions of sections 3 and 10; T2N R17E, all or portions of sections 24, 25, 26, 34, and 35; and T2N R18E, all or portions of sections 18, 19, and 30. |
Environmental Assessment · Ashley National Forest All Units · updated 12/10/2019
The project will extend from Vernal, Utah to Dutch John and Manila, Utah and will parallel and be located adjacent to Highways 191 and 44. · Daggett; Uintah, Utah
Strata Networks is proposing to install approximately 75 miles of high speed fiber optic cable from Vernal, Utah to the communities of Dutch John and Manila, utilizing the Highway 191 and 44 corridors.
Special use management
Comment Period
01/24/2017
Objection Period Start
04/25/2017
Decision
06/2017 (Estimated)
Implementation
06/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District; Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Roosevelt Ranger District · updated 12/10/2019
Seven locations in the Swift Creek Watershed. · Duchesne, Utah
We are proposing to construct hiking trail reroutes at 7 selected locations in the Swift Creek Focus Watershed. The project would total approximately 4,600 feet of trail construction and 3,300 feet of trail closures and rehabilitation.
Recreation managementWatershed management
Decision
04/2014 (Estimated)
Implementation
06/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management; Watershed Improvements; Wilderness Management |
| Swift Creek Watershed Trail Relocations Decision Memo | Decision Signed Date: 04/24/2014 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | SE, Sec 20, T3N, R4W; SW, SE, Sec 5, T3N, R4W; NW, NW, Sec 5, T3N, R4W; NW, SE, Sec 32, T4N, R4W; NE, NE, Sec 32, T4N, R4W; NW, NE, Sec 4, T3N, R4W; SE, SW, Sec 4, T3N, R4W Uintah Base Meridian |
Environmental Assessment · Flaming Gorge Ranger District · updated 12/10/2019
Ashley National Forest - Flaming Gorge Ranger District. Utah - Daggett County. Located approximately 3 miles southeast of Manila, Utah immediately adjacent to and east of the Manila landfill. · Daggett, Utah
Land conveyance to the Town of Manila to expand the town's landfill. The land proposed for conveyance is located immediately adjacent to and east of the landfill. The current landfill is nearing capacity.
Land ownership management
Comment Period
10/14/2014
Objection Period Start
12/16/2014
Decision
03/2015 (Estimated)
Implementation
04/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Land Exchanges |
| Town of Manila Land Conveyance (Manila Landfill) | Decision Signed Date: 03/06/2015 |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | SLM&B, T. 2N., R.20E., section 5, A portion of Lot 2 |
Decision Memo · Ashley National Forest All Units · updated 12/10/2019
This project is in Whiterocks Canyon, approximately 18 miles north west of the town of Lapoint, Utah in Uintah County, and is accessed by County Highway 246 from LaPoint. · Uintah, Utah
Special use permit renewal for the operation and maintenance of the Red Pine Spring water system and the Unnamed Spring water system along with the associated valves and water transmission lines that deliver the water to the private lands.
Special use management
Decision
07/2016 (Estimated)
Implementation
08/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | T2N, R1E, SEC. 17 & 18, USM. |
Environmental Assessment · Vernal Ranger District · updated 12/10/2019
Whiterocks Canyon (on the southwestern edge of the Vernal Ranger District) · Uintah, Utah
This project includes campground vegetation management, fuel breaks, an emergency pullout, and ponderosa pine restoration and maintenance in Whiterocks Canyon.
Forest productsVegetation management (other than forest products)Fuels management
Comment Period
01/26/2016
Objection Period Start
05/03/2016
Decision
06/2016 (Estimated)
Implementation
07/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Hfra Title I: Wildland-Urban Interface; Hfra Title I: Threats To Ecosystem Components (Such As Insect Or Disease Epidemics) |
| Notice and Comment Regulation | 218 (2013) HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green) |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | T2N R1E, sections 5-7; T2N R1W, sections 1 and 12; T3N R1E, sections 30-32; T3N R1W, sections 21-28 and 35-36; all Uintah Meridian |
Decision Memo · Duchesne Ranger District · updated 12/10/2019
This project will reroute a section of the Yellowstone Trail (057) approximately 4 miles from the Swift Creek Trailhead traveling up-drainage. The Swift Creek Trailhead is located ~40mi N of Duchesne. · Duchesne, Utah
This project aims to reroute a 0.05 mi section of the Yellowstone Trail (057) that is currently being undercut by Yellowstone Creek. The reroute will place the trail up slope of the current trail in a talus field protected from further undercutting.
Recreation management
Decision
02/2019 (Estimated)
Implementation
08/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | NW1/4 NE1/4 Section 36 Township 3N Range 5W |
Environmental Assessment · Roosevelt Ranger District · updated 11/8/2019
The project location is approximately 25 miles Southwest of Duchesne, Utah · Duchesne, Utah
The Ashley NF proposes to modify the Sowers Canyon portion of the Duchesne Roosevelt District Wide Range Improvement Project. The project includes an additional 4 miles pipeline, 5 additional trough locations and two 10,000 gal storage tanks.
Grazing management
Comment Period
07/16/2019
Objection Period Start
09/03/2019
Decision
10/2019 (Estimated)
Implementation
10/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Structural Improvements |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Sections 24, 25, 26, 27, 29, 32, 33, 35 T 6 S, R 6 W, Salt Lake Base Meridian |
Decision Memo · Duchesne Ranger District · updated 11/5/2019
South from Duchesne UT on HWY 191 for 28.25 miles, turn east on Argyle Canyon Rd, in 1/2 mile turn North on road that access Badland Cliffs, 0.3 miles road T's project starts here going east for 2 mi. · Duchesne, Utah
Create a shaded fuel break along FS boundary and Argyle Badland Cliff access road by removing hazardous fuels by means of limbing and thinning to compliment UT State Forestry and Fire and private landowner firewise efforts in the area.
Fuels management
Decision
10/2019 (Estimated)
Implementation
11/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Township 7 South, Range 8 West Section 12 and Township 7 South, Range 7 West, Sections 7 & 8. |
Decision Memo · Duchesne Ranger District · updated 8/9/2019
40.65998 N, 110.1772 W ~ 3 miles from the Trailhead · Duchesne, Utah
Roughly 0.15 miles of the Uinta River Trail have been covered in water by newly constructed beaver dams. This has made the trial impassible to hikers and stock. A 0.25 mile trail reroute is proposed to address the loss of trail access.
Recreation management
Decision
07/2019 (Estimated)
Implementation
08/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Uinta Beaver Dam Trail Reroute | Decision Signed Date: 07/17/2019 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | SE1/4 NW1/4 ,Section 13, T3N R3W |
Decision Memo · Ashley National Forest All Units · updated 3/28/2019
Lot #18 in the Oaks Park Summer Home tract, near Oaks Park Reservoir · Uintah, Utah
to issue a special use permit to the Oaks Park Summer Home Association for the continued operation and maintenance of the existing water well and pump house located in the Oaks Park Summer Home tract.
Special use management
Decision
03/2019 (Estimated)
Implementation
04/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | North 1,088 feet West 2,730 feet from the SE corner, SEC. 12, T.1.S., R.20.E., SLBM. |
Decision Memo · Flaming Gorge Ranger District · updated 2/28/2019
Lucerne Valley Marina, Flaming Gorge Reservoir · Daggett, Utah
Amendment of an existing special use authorization for Flaming Gorge Corp to build a 36-slip transient boater docking facility and attenuator at Lucerne Valley Marina.
Special use management
Decision
02/2019 (Estimated)
Implementation
04/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 2/8/2019
Project is located along the North side of Dutch John Mountain and Antelope Flat. The project is bisected by the Antelope Flat boat launch road and runs parallel and easterly across Hwy 191 · Daggett, Utah
Pinyon and juniper trees encroaching into sagebrush communities will be mulched or lopped, scattered and otherwise left in place. Objective is to maintain the sagebrush community for sage-grouse and to maintain native vegetative diversity.
Wildlife, fish, rare plantsVegetation management (other than forest products)
Decision
10/2018 (Estimated)
Implementation
07/2019 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements; Rangeland Vegetation Improvements |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | T3N, R21E, portions of Sections 25, 26, 27, 33, 34, 35, 36, and R22E portions of Sections 29, 30, 31, 32, 33, 34 in Daggett County, Utah |
Decision Memo · Vernal Ranger District · updated 10/31/2018
South slope of the Uinta Mountains north of Vernal, Utah on the Flaming Gorge-Vernal and Roosevelt-Duchesne Ranger Districts within Uintah, Daggett, and Duchesne Counties. · Daggett; Duchesne; Uintah, Utah
Hand treatment of encroaching conifers using chainsaws throughout the meadows of the south slope of the Uinta Mountains.
Vegetation management (other than forest products)
Decision
10/2018 (Estimated)
Implementation
10/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Rangeland Vegetation Improvements |
| Forests | Ashley National Forest |
| Districts | Ashley National Forest All Units |
| Legal Land Description | Salt Lake Meridian T1N R18-22E; T1S R18-22E; T2S R18-22E and Uintah Meridian T5N R1-2W; T4N R1-2W; T3N R1-5W; T2N R5W with numerous sections |
Environmental Assessment · Ashley National Forest All Units · updated 10/15/2018
The Ubar Ranch is located in Uinta Canyon on the Duchesne Ranger District of the Ashley National Forest (T3N, R2W, Sec 19, Uintah Special Meridian). · Duchesne, Utah
The proposed action is to reduce the safety hazards and to meet the requirements of the terminated special use permit by removing all improvements and restoring the UBAR Ranch area back to its natural condition.
Special use management
Comment Period
05/22/2018
Objection Period Start
08/21/2018
Decision
10/2018 (Estimated)
Implementation
10/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T3N, R2W, Sec 19 Uintah Special Meridian |
Decision Memo · Vernal Ranger District · updated 9/13/2018
Gull Lake, Lake Canyon, Flat Springs, Sawtooth Ridge, Sink Ridge · Uintah, Utah
Construction of six guzzlers in the Lake Mountain area.
Wildlife, fish, rare plantsGrazing managementVegetation management (other than forest products)
Decision
09/2018 (Estimated)
Implementation
10/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Species Population Enhancements; Rangeland Vegetation Improvements; Grazing Structural Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | T2SR19E Sections 34, 35, 26, 21 |
Decision Memo · Ashley National Forest All Units · updated 8/22/2018
North of Riverview Campground off of forest road 124 · Duchesne, Utah
Yellowstone Creek's main channel became altered during a recent flood event. The new location of the channel provides a hazard to the Riverview Campground. Work would be completed using rock barbs to restore flow patterns in the former channel.
Watershed managementFacility management
Decision
08/2018 (Estimated)
Implementation
08/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (19), 36 Cfr 220.6(E)(19) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Riverview Campground Bank Stabilization CE | Decision Signed Date: 08/17/2018 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | T2N R4W Section 9 NENE Uintah Basin Special Meridian |
Environmental Assessment · Duchesne Ranger District · updated 8/9/2018
The Honeycomb Mine is within the Blind Stream drainage of the Duchesne District of the Ashley NF. At the end of Forest System road 121, in the North 1/2 of Section 28, T2N R8W, Uinta Meridian. · Duchesne, Utah
A new Plan of Operations was submitted for continued operations at the Honeycomb Mine. Large blocks of decorative calcite will be removed from the mine. Up to 2.5 acres active disturbance proposed. Disturbed areas not needed would be reclaimed.
Minerals and geology
Comment Period
12/08/2015
Objection Period Start
02/02/2016
Decision
05/2016 (Estimated)
Implementation
06/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Honeycomb Mine Project | Decision Signed Date: 05/11/2016 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Mine located within North 1/2 of Section 28, T2N R8W, Uinta Meridian. |
Environmental Assessment · Duchesne Ranger District · updated 8/9/2018
The Strawberry Peak allotment is located on the South Unit of the Ashley National Forest. · Duchesne, Utah
The Roosevelt-Duchesne Ranger District proposes to convert the Strawberry Peak allotment on the Ashley National Forest from sheep to cattle.
Grazing management
Comment Period
03/01/2016
Objection Period Start
05/03/2016
Decision
05/2017 (Estimated)
Implementation
06/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Allotment Management |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Strawberry allotment occurs in portions of: 1) T4S. R9W. 2) T5S. R9W. 3) T5S. R9W. 4) T5S. R10W. 5) T6S. R9W. 6) T6S. R10W. USM |
Environmental Assessment · Roosevelt Ranger District · updated 8/1/2018
District wide. · Duchesne, Utah
Installation of 5.7 miles of fence and extend 11 livestock water systems which would include pipe installation, new troughs and water holding tanks. All proposed water developments will connect into existing livestock water systems.
Grazing management
Comment Period
12/01/2015
Objection Period Start
06/05/2018
Decision
07/2018 (Estimated)
Implementation
08/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Structural Improvements |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 5/22/2018
Oaks Park WL is located in Grasshopper Flat on Taylor Mtn. UBTA phone line is located off shoulder of FSR 492 in Whiterocks Cyn. UBTA phone line is located in Rock Creek Cyn off shoulder of FSR 134. · Duchesne; Uintah, Utah
1.Permit renewal for lower section of Oaks Park Canal Waterline to Ashley Valley Reservoir Co. 2.Permit renewal for Whiterocks Canyon telephone line to UBTA. 3.Permit renewal for Rock Creek telephone/fiber line to UBTA. All are existing facilities.
Special use management
Decision
05/2018 (Estimated)
Implementation
08/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District; Duchesne Ranger District |
| Legal Land Description | 1.Oaks Park Canal-PB 37, T2S,R20E,SLM / 2.Whiterocks Canyon- NE1/4 SE1/4, SEC.18, T2N, R1E, USM / 3.Rock Creek Canyon- SEC.4&5, T1N, R6W; SEC.32&31, T2N, R6W; SEC.36,25,26,27,28,21&20, T2N, R7W, USM. |
Environmental Impact Statement · R4 - Intermountain Region All Units · updated 3/20/2018
This project initiates in central Wyoming and crosses public, private, and state lands in Wyoming, Colorado, Utah, and Nevada. · Beaver; Duchesne; Emery; Garfield; Iron; Juab; Millard; Piute; Sevier; Uintah; Wasatch; Weber, Utah
This proposed 600 kV direct current transmission line is designed to carry renewable energy (primarily wind power) from generation sources in central Wyoming to markets in in the pacific southwest
Special use management
NOI in Federal Register
01/04/2011
DEIS NOA in Federal Register
02/18/2011
FEIS NOA in Federal Register
01/13/2017
Objection Period Start
01/21/2017
Decision
05/2017 (Estimated)
Implementation
03/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Transwest Express Transmission Project | Decision Signed Date: 05/31/2017 |
| Forests | Ashley National Forest; Dixie National Forest; Fishlake National Forest; Manti-Lasal National Forest; Uinta-Wasatch-Cache National Forest |
| Districts | Roosevelt Ranger District; Pine Valley Ranger District; Fillmore Ranger District; Richfield Ranger District; Ferron Ranger District; Heber-Kamas Ranger District; Spanish Fork Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Flaming Gorge Ranger District · updated 11/20/2017
The new office would be located directly behind the small, existing ranger station located at 25 West Highway 43 in Manila, UT. · Daggett, Utah
This project would involve the construction of a new, consolidated office in Manila, UT for the northern end of the Flaming Gorge-Vernal Ranger District.
Facility management
Comment Period
08/29/2017
Decision
11/2017 (Estimated)
Implementation
01/2018 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Salt Lake Meridian: Township 3 North, Range 19 East, a portion of section 24 |
Environmental Assessment · Ashley National Forest All Units · updated 11/3/2017
The project is located in Sower's Canyon, approximately 14 miles southwest of Duchesne, Utah. · Duchesne, Utah
This project would reinstate an existing class II lease to Berry Petroleum Company. The BLM would issue the lease to Berry Petroleum and the Forest Service would provide consent to lease.
Minerals and geology
Comment Period
07/25/2017
Objection Period Start
09/12/2017
Decision
11/2017 (Estimated)
Implementation
11/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Nepa Document Prepared By Another Federal Agency; Ira - Inventoried Roadless Area Activities Requiring Chief's Approval |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Natural Gas; Oil |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T6S, R5W, Sections 7, 8, and 18. |
Decision Memo · Ashley National Forest All Units · updated 10/6/2017
The project is located is Government Park and Windy Park near Oaks Park Reservoir. · Uintah, Utah
Government Creek and Windy Park are both high quality wet meadows. Both meadows have experienced erosion that drying up the wet meadows. Restoration using grade control structures will be used to restore function and control additional erosion.
Wildlife, fish, rare plantsWatershed management
Decision
09/2017 (Estimated)
Implementation
10/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (20), 36 Cfr 220.6(E)(20) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | T1S R20E Section 11 E1/2, Section 2 NENE |
Decision Memo · Ashley National Forest All Units · updated 9/13/2017
The phone/fiber line is in N.F. Duchesne Cyn, the Power Line is in N.F. Duchesne & Rock Creek Cyn, the Water Line is in Lake Fork Cyn, the Burton Canals & the Whiterocks Lake Dam is on the Vernal RD. · Duchesne; Uintah, Utah
Renew SUPs for: 1.NF Duchesne Phone/Fiber Line - UBTA. 2. NF Duchesne/Rock Creek Power Line - MLEA. 3. Lake Fork-Moon Lake Water Line - MLWUA. 4. Burton Reservoir Canals - Rosemary Murdock. 5. Whiterocks Lake Dam/Reservoir - Ouray Park Irrigation Co.
Special use management
Decision
08/2017 (Estimated)
Implementation
08/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District; Roosevelt Ranger District; Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Vernal Ranger District · updated 8/31/2017
Across the Vernal Ranger District · Uintah, Utah
Miscellaneous range improvement projects (water developments, fences, etc.) on seven grazing allotments on the Vernal Ranger District.
Grazing management
Comment Period
05/16/2017
Objection Period Start
07/04/2017
Decision
08/2017 (Estimated)
Implementation
09/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Allotment Management; Grazing Structural Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Duchesne Ranger District · updated 7/20/2017
The landslide is located in Uinta Canyon on the slope above U-Bar Ranch on the Duchesne Ranger District · Duchesne, Utah
The proposed project would remove a debris plug within a landslide that occurred in 2005. Removal of the plug would reroute the flow of additional debris away from the wetland and spring pond at Smokey Spring in Uinta Canyon on the Duchesne District.
Watershed managementRecreation managementWildlife, fish, rare plants
Decision
07/2017 (Estimated)
Implementation
07/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (19), 36 Cfr 220.6(E)(19) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Dispersed Recreation Mgmt.; Species Habitat Improvements; Scenery Management; Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | The landslide is located in Uinta Canyon on the south slope above U-Bar Ranch on the Duchesne Ranger District. T. 3 N., R.2 W. Section 19, USM. |
Environmental Impact Statement · Uinta-Wasatch-Cache All Units · updated 7/19/2017
The project initiates in central Wyoming and crosses public, private, and state lands in Wyoming, Colorado, and Utah. Project terminates at the Mona substation in central Utah. · Beaver; Duchesne; Emery; Garfield; Iron; Juab; Millard; Piute; Sevier; Uintah; Wasatch; Weber, Utah
This proposed 500 kV transmission line is designed to deliver power to Rocky Mountain Power utility costumers in Utah and the intermountain west. Generation sources are located in central Wyoming.
Special use management
NOI in Federal Register
04/01/2011
DEIS NOA in Federal Register
04/01/2011
FEIS NOA in Federal Register
01/13/2017
Objection Period Start
01/21/2017
Decision
05/2017 (Estimated)
Implementation
01/2020 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Energy Gateway South Transmission Project | Decision Signed Date: 05/31/2017 |
| Forests | Ashley National Forest; Dixie National Forest; Fishlake National Forest; Manti-Lasal National Forest; Uinta-Wasatch-Cache National Forest |
| Districts | Duchesne Ranger District; Pine Valley Ranger District; Fillmore Ranger District; Richfield Ranger District; Price Ranger District; Heber-Kamas Ranger District; Spanish Fork Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 3/22/2017
Dutch John Bench is 1.5 miles N of Dutch John, Jarvie is 4 miles NW of Dutch John. Dowd is on near Forest Roads 094 and 613 on Dowd Mountain off of Hwy 44. · Daggett, Utah
Construction of 3 individual 1,800 gallon precipitation water catchment aprons and storage tank/drinkers in 3 separate locations on the Flaming Gorge Ranger District. Improved water distribution and security would be provided for local wildlife
Wildlife, fish, rare plants
Decision
03/2017 (Estimated)
Implementation
05/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Species Population Enhancements |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Jarvie Draw Site T3N R22E SE1/4 Sec36; Dutch John Bench Site T2N R22E NE1/4 of SW1/4 Sec 13; Dowd Mtn Site T2N R20E NE1/4 of SW1/4 Sec 26 |
Decision Memo · Ashley National Forest All Units · updated 9/27/2016
East Park Reservoir located ~30 miles north of Vernal, Utah on Hwy.191 and FSR #020. Little Brush Creek Waterline located ~22 miles north of Vernal, Utah on Hwy.191 and FSR #278. · Uintah, Utah
Renew a special use permit to the Division of Wildlife Resources to operate and maintain the East Park Reservoir, dam, and spillways. Renew a special use permit to the Sunshine Canal Company to operate and maintain a waterline in Little Brush Creek.
Special use management
Decision
09/2016 (Estimated)
Implementation
12/2016 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | East Park Reservoir - Sec.27,28,33,34,T1N,R21E,SLM. Little Brush Creek Waterline - Sec.30,T1S,R22E,and Sec.24,25,T1S,R21E,SLM. |
Environmental Assessment · Vernal Ranger District · updated 9/30/2015
Bowden Draw and Greens Draw in the Cart Creek Watershed, located east of Hwy 191. · Uintah, Utah
We are proposing to reroute and rehabilitate a 1.33 mile segment of Forest Road 49 and a 1.35 mile segment of Forest Road 177. This proposed project also includes seasonal closures of portions of FR 49 and FR 177 and Forest Trails 3, 4, and 8.
Wildlife, fish, rare plantsRoad managementRecreation managementWatershed management
Comment Period
06/09/2015
Objection Period Start
07/21/2015
Decision
09/2015 (Estimated)
Implementation
10/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Travel Management; Watershed Improvements |
| Revised Cart Creek Watershed Roads Improvement Project | Decision Signed Date: 09/30/2015 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | T 1N, R 22E, Sec 2, 10 - 12, 15, 16, 21 - 24, 27, 28. T1N, R23E, Sec 7. Salt Lake Meridian |
Decision Memo · Duchesne Ranger District · updated 9/30/2015
Lower Corral Creek, in the Rock Creek area of the Ashley National Forest. Within the SE 1/4 of section 8, T1N R8W Uintah Meridian · Duchesne, Utah
Short-term exploratory drilling operation for locatable minerals, located near the mouth of Corral Creek in the Lower Rock Creek area of the Ashley National Forest. Up to 4 drill holes, each up to 200 feet deep. Expected 1 week project duration.
Minerals and geology
Comment Period
05/22/2015
Decision
09/2015 (Estimated)
Implementation
09/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Kenya's Quest Exploratory Drilling Project | Decision Signed Date: 09/08/2015 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | SE1/4 of section 8, T1N R8W Uintah Meridian |
Decision Memo · Duchesne Ranger District · updated 9/9/2015
10.5 miles NW of Hanna, UT, Crossing of FR 144 and Hades Creek · Duchesne, Utah
Replacement of the bridge spanning Hades Creek, near Hades Creek Campground.Hades Creek Bridge is located along the North Fork Duchesne Road FSR10144.
Road management
Decision
06/2015 (Estimated)
Implementation
10/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T2N R9W S1/2 of Section 26 UBSM |
Environmental Impact Statement · Uinta-Wasatch-Cache All Units · updated 8/14/2015
The project is located in the High Uintas Wilderness in both Duchesne and Summit counties. The project is located northeast of Duchesne, UT and southwest of Manila, UT. · Duchesne; Summit; Uinta, Utah; Wyoming
This is a duplicate entry. For information on the project, follow the link "High Uintas Wilderness Domestic Sheep Analysis Project (Ashley and UWC National Forests)" below.
Grazing management
NOI in Federal Register
08/2015 (Estimated)
DEIS NOA in Federal Register
10/2016 (Estimated)
FEIS NOA in Federal Register
03/2017 (Estimated)
Objection Period Start
03/2017 (Estimated)
Decision
08/2017 (Estimated)
Implementation
09/2017 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Allotment Management; Grazing Authorizations |
| Forests | Ashley National Forest; Uinta-Wasatch-Cache National Forest |
| Districts | Roosevelt Ranger District; Duchesne Ranger District; Evanston-Mountain View RD |
| Legal Land Description | Not Applicable |
Decision Memo · Ashley National Forest All Units · updated 8/5/2015
The proposed project is within the Flaming Gorge Ranger District located approximately 2 miles NW of Dutch John, Utah. Accessed by traveling north on Hwy 191 just beyond FS Road 184. · Daggett, Utah
Install a precipitation collection apron and a combination fiberglass tank and watering trough. The precipitation collection apron is approximately 20 feet wide and 50 feet long. The tank holds 1800 gallons.
Wildlife, fish, rare plants
Decision
08/2015 (Estimated)
Implementation
08/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Mustang Ridge Wildlife Water Guzzler Project | Decision Signed Date: 08/05/2015 |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Township 3 North, Range 22 East, SE 1/4 Section 32, Daggett County, Utah |
Decision Memo · Ashley National Forest All Units · updated 6/14/2015
Areas will be located on the Vernal and Flaming Gorge Ranger Districts · Daggett; Duchesne; Summit; Uintah, Utah
This project will remove all dead and dying trees within the Flaming Gorge and Vernal Ranger District campgrounds and high-use areas listed. Campgrounds and high-use areas will be reated with insecticide and anti-agression pheremones as needed.
Recreation managementVegetation management (other than forest products)
Decision
10/2010 (Estimated)
Implementation
06/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5); 32.2 (14), 36 Cfr 220.6(E)(14) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Forest Vegetation Improvements; Dispersed Recreation Mgmt.; Scenery Management |
| Flaming Gorge and Vernal Ranger Districts Campground Insect Suppression | Decision Signed Date: 10/25/2010 |
| Forests | Ashley National Forest |
| Districts | Ashley National Forest All Units |
| Legal Land Description | Multiple areas on the Vernal and Flaming Gorge Ranger Districts (please see Decision Memorandum for details) |
Decision Memo · Ashley National Forest All Units · updated 6/10/2015
Whiterocks project is located approx. 3.5 miles up the canyon from the Forest Boundary on FR 492. Uinta Canyon project is located approx. 2 miles up the canyon from the Forest Boundary on FR 118. · Duchesne; Uintah, Utah
To issue a temporary permit for borehole drilling and test pit excavations in designated areas within Whiterocks and Uinta Canyons. Project purpose is to extract core samples of geologic material to determine engineering properties of native material
Special use management
Decision
06/2015 (Estimated)
Implementation
06/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 06/03/2015 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District; Roosevelt Ranger District |
| Legal Land Description | Sec.31,T3N,R1E,and Sec.6,T2N,R1E,and Sec.30,29,32, T3N,R2W, USB&M. |
Decision Memo · Ashley National Forest All Units · updated 2/27/2015
Adjacent to the S Fk Rock Creek, near the confluence with Rock Creek, 1 mi below Upper Stillwater Dam, 31 mi NW of Duchesne, UT. · Duchesne, Utah
The Forest proposes actions to stabilize a gully and cutbank bordering the floodplain of the South Fork Rock Creek. Stabilization efforts will alleviate erosion that is delivering sediment to the South Fork of Rock Creek and its surrounding wetland.
Special use managementWatershed management
Decision
09/2014 (Estimated)
Implementation
10/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (19), 36 Cfr 220.6(E)(19) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Area Management; Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | SW Sec 21, T2N, R7W, Uintah Base Meridian |
Environmental Assessment · Roosevelt Ranger District · updated 2/12/2015
West shoreline of Moon Lake adjacent to the developed campground in Lake Fork Canyon on the Roosevelt-Duchesne Ranger District of the Ashley National Forest. · Duchesne, Utah
The proposed project would improve boating access to Moon Lake by installing a concrete boat ramp and paved parking area. The proposed ramp measures 800' long by 20' wide with 85' by 85' turnaround areas every 200'.
Recreation management
Comment Period
09/23/2014
Decision
02/2015 (Estimated)
Implementation
07/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction |
| Moon Lake Boat Ramp Decision Notice | Decision Signed Date: 02/12/2015 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Flaming Gorge Ranger District · updated 12/4/2014
Located in Section 29, T2N, R22E, SLM, Daggett County, Utah. · Daggett, Utah
Modify existing permit to all for the construction a new water treatment plant, install a new partially buried water tank and construct a 700 square yard gravel parking area within the existing site boundary.
Special use management
Decision
12/2014 (Estimated)
Implementation
12/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Greendale Water Company Amendment | Decision Signed Date: 12/01/2014 |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Located in Section 29, T2N, R22E, SLM, Daggett County, Utah. |
Decision Memo · Ashley National Forest All Units · updated 11/18/2014
The well pad, and any needed road upgrades or new road construction, would be located on Wildhorse Ridge, within section 1, T6S R6W Uinta Meridian. · Duchesne, Utah
Proposal from Vantage Energy to construct a single new well pad, on existing oil and gas leases, in the Wildhorse Ridge area of the South Unit, then drill up to 4 oil and gas wells from that pad.
Minerals and geology
Decision
11/2014 (Estimated)
Implementation
12/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (3) |
| Special Authority | Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390) |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Natural Gas; Oil |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | The well pad, along with any road upgrades or new road construction, would be located with Section 1, T6S R6W, Uinta Meridian. |
Decision Memo · Flaming Gorge Ranger District · updated 8/26/2014
Multiple locations on the Flaming Gorge Ranger District located near Manila Utah, Green River Wyoming, Buckboard Marina Wyoming and Dutch John Utah. · Daggett; Uintah; Sweetwater, Utah; Wyoming
Four special use permits located on the Flaming Gorge Ranger District that are expired or expiring and are being requested for reauthorization.
Special use management
Decision
07/2014 (Estimated)
Implementation
08/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Vernal Ranger District · updated 8/26/2014
Mosby Mountain-23 miles north of Lapoint, Utah on Mosby Mountain Road · Uintah, Utah
This project would involve the construction of a pipeline from Mosby Canal to the lower pastures of Mosby Mountain Allotment to provide a reliable water source for cattle.
Grazing management
Comment Period
10/2014 (Estimated)
Objection Period Start
12/2014 (Estimated)
Decision
02/2015 (Estimated)
Implementation
05/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Structural Improvements |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Salt Lake Meridian T2S, R18E, Sec 22, 27, 34, 35; T3S, R18E, Sec 2, 10, 11 Uintah Meridian T2N, R1E Sec 9, 16 |
Decision Memo · Ashley National Forest All Units · updated 8/13/2014
Cliff Lake Reservoir · Uintah, Utah
Reissuance of a 10 year Special Use Permit to the Ouray Park Irrigation Company allowing them to impound water in the Cliff Lake Reservoir for agricultural use as well as repair the dam at Cliff Creek Reservoir
Special use managementWatershed management
Decision
08/2014 (Estimated)
Implementation
09/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Cliff Lake Dam Repair Project Decision Memo | Decision Signed Date: 08/11/2014 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Salt Lake Meridian, T1S,R17E, Section 22 |
Decision Memo · Vernal Ranger District · updated 5/12/2014
The project is located approximately 8 miles north of the Red Cloud Loop Road at it's junction with the Dry Fork Canyon Road, and about 16 miles northwest of Vernal, UT. · Uintah, Utah
Relocation of approximately 1 mile of the Flume Trail from private land to Forest Service lands. The project would also include construction of one trail bridge.
Land ownership managementRecreation management
Decision
02/2014 (Estimated)
Implementation
06/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Flume Trail Relocation Project | Decision Signed Date: 02/13/2014 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Duchesne Ranger District · updated 3/26/2014
Headwaters of Iron Mine Creek, Wasatch County, Utah · Wasatch, Utah
A proposal for short-term small-scale hard-rock mining operations in the upper Iron Mine Creek area of the Ashley National Forest (Section 19, T2N R9W, Uinta Meridian).
Minerals and geology
Comment Period
05/2014 (Estimated)
Objection Period Start
07/2014 (Estimated)
Decision
09/2014 (Estimated)
Implementation
10/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Northern ½ of Section 19, T2N R9W, Uinta Meridian |
Environmental Assessment · Duchesne Ranger District · updated 3/26/2014
Rhoades Canyon area on the west side of the Duchesne Ranger District · Duchesne, Utah
Proposal to purchase and remove up to 2,000 tons per year of rocks, for up to 10 years, for commercial construction purposes. Rocks would be from within Rhoades Canyon, on the Duchesne District of the Ashley National Forest.
Minerals and geology
Comment Period
02/2014 (Estimated)
Objection Period Start
03/2014 (Estimated)
Decision
03/2014 (Estimated)
Implementation
06/2014 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | The proposed rock removal area is located within or near the SW ¼ of SW ¼ of Section 3, T1N R9W, Uintah Meridian. |
Decision Memo · Flaming Gorge Ranger District · updated 9/19/2013
Adjacent to the existing residential housing unit at Cedar Springs Marina. The Marina is located 40 miles north of Vernal, Utah on US Highway 191 and 2 miles west of the Flaming Gorge Dam. · Daggett, Utah
We are proposing the construction of a 30-ft. wide x 40-ft. long x 20-ft. tall garage on the current parking area adjacent to the existing residential housing unit at Cedar Springs Marina.
Special use management
Decision
08/2013 (Estimated)
Implementation
10/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Duchesne Ranger District · updated 6/3/2013
Duchesne, Utah · Duchesne, Utah
A single story, 10 person bunkhouse would be constructed in Duchesne along with an associated parking area. The building would be accessible, meet current building and zoning codes, and be built on property owned by the Forest Service.
Facility management
Comment Period
08/14/2012
Decision
09/2012 (Estimated)
Implementation
06/2015 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Facility Improvements/Construction |
| Duchesne Bunkhouse Construction | Decision Signed Date: 09/27/2012 Legal Notice Date: 10/02/2012 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Flaming Gorge Ranger District · updated 6/3/2013
Approximately eight miles southwest of Manila, Utah. · Daggett, Utah
Extend the Sheep Creek Lake ATV Trail to provide improved connectivity to Ute Tower, Death Valley, and the Summit Springs Guard Station. Also develop a small barrier rock pit to facilitate trail construction and motorized travel plan implementation.
Recreation management
Comment Period
02/16/2012
Decision
06/2012 (Estimated)
Implementation
07/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management; Travel Management |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | T2N., R19E., Secs. 26, 27, 28 & 30, SLM |
Environmental Impact Statement · Duchesne Ranger District · updated 6/3/2013
Northern portion of the South Unit, roughly between Antelope and Sowers Canyons. · Duchesne, Utah
Berry Petroleum is proposing to drill up to 400 oil and gas wells in the northern portion of the South Unit of the Ashley National Forest.
Minerals and geology
NOI in Federal Register
08/29/2007
DEIS NOA in Federal Register
02/26/2010
FEIS NOA in Federal Register
02/24/2012
Decision
02/2012 (Estimated)
Implementation
06/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Ira - Inventoried Roadless Area Activities Requiring Secretary/Undersecretary Approval |
| Notice and Comment Regulation | 215 |
| Project Activity | Minerals Or Geology Plans Of Operations |
| south Unit Oil and Gas Development FEIS | Decision Signed Date: 02/21/2012 Legal Notice Date: 02/29/2012 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Duchesne Ranger District · updated 4/10/2013
Gilsonite Ridge area of the South Unit of the Ashley National Forest · Duchesne, Utah
Proposal for 16 new oil and gas wells on 4 new well pads, and 9 new wells on 3 previously approved well pads, in the Gilsonite Ridge area. About 1.2 miles of new roads, and about 1 mile of road upgrades, would be needed for safe project access.
Minerals and geology
Comment Period
10/30/2012
Decision
04/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Oil |
| Decision Memo Vantage 2013 Oil and Gas Project | Decision Signed Date: 04/01/2013 Legal Notice Date: 04/09/2013 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Proposed well pads in Sections 4, 5, and 6 of T6S R3W, Uinta Meridian. Previously approved well pads in Sections 6, 7, and 20 of T6S R3W, Uinta Meridian. |
Environmental Assessment · Vernal Ranger District · updated 2/28/2013
The new trailhead location would be 1.6 miles further up canyon at the intersections of Forest Roads 018 and 031. · Uintah, Utah
A DN/FONSI on the Dry Fork Flume Trailhead was signed in August 2011. Due to private in-holding access issues, a new location for the trailhead further up canyon has now been identified which would better facilitate all-around winter use.
Recreation management
Comment Period
08/01/2012
Decision
02/2013 (Estimated)
Implementation
04/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Developed Site Management; Plan Amendment |
| Flume Trailhead Relocation Project | Decision Signed Date: 02/22/2013 Legal Notice Date: 02/27/2013 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | T2S R19E, Sec. 26, SLM |
Decision Memo · Flaming Gorge Ranger District · updated 12/12/2012
Forest Service designated boat ramps, located at Lucerne Marina, Flaming Gorge NRA · Daggett, Utah
Flaming Gorge Ranger District is proposing to issue this permit for a term up to 20 years for the continued operation of Wakeless Harbor to launch, recover, test and perform minor repairs of boats and marine equipment on the Flaming Gorge Reservoir
Special use management
Comment Period
04/25/2012
Decision
12/2012 (Estimated)
Implementation
01/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
Decision Memo · Vernal Ranger District · updated 11/28/2012
Grizzly Ridge Communication Site · Uintah, Utah
Renewal of a communication use lease and the construction of a new generator building within the established limits of the State of Utah/Division of Information Technologys authorized area, located at the Grizzly Ridge Communication Site.
Special use management
Comment Period
05/30/2012
Decision
09/2012 (Estimated)
Implementation
10/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| State of Utah at Grizzly Ridge Comm Site | Decision Signed Date: 09/19/2012 Legal Notice Date: 09/26/2012 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | NW1/4NW1/4NW1/4, sec. 17, T. 1 S., R. 22 E., SLM. Uintah County, Utah |
Decision Memo · Vernal Ranger District · updated 11/1/2012
The project is located approximately 20 miles north of Vernal, UT and can be reached by traveling north on U.S. Hwy 191. Treatment areas are on either side of 13 miles of Hwy. 191. · Daggett, Utah
Removal of dead trees to reduce hazards associated with trees toppling into roadways and onto trails, reduce hazardous fuels build-up, and to capture the economic value of the trees. Also, manipulation of stand densities to promote healthy trees.
Fuels managementVegetation management (other than forest products)
Comment Period
05/23/2012
Decision
10/2012 (Estimated)
Implementation
05/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage); Timber Sales (Green) |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | SLM - T1N, R22E, all or portions of sections 5, 8, 17, 31, and 32; T1S, R21E, all or portions of section 5; and T1S R22E, all or portions of sections 5, 8, 17, and 30. |
Decision Memo · Duchesne Ranger District · updated 9/25/2012
The project is located on Anthro Mountain south of Duchesne Utah. · Duchesne, Utah
Removal of encroaching conifers in sagebrush and mountain brush communities for the benefit of sagebrush and mountain brush obligate wildlife species.
Wildlife, fish, rare plants
Comment Period
04/24/2012
Decision
09/2012 (Estimated)
Implementation
08/2013 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements |
| Upper Anthro Mountain Lop and Scatter Project | Decision Signed Date: 09/17/2012 Legal Notice Date: 09/25/2012 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | The project occurs in the southern mile sections of T6S, R3W; T6W, R5W; T6W, R6W; and portions of T7S, R4W and T76R5W. |
Decision Memo · Flaming Gorge Ranger District · updated 9/17/2012
Approximately 2.5 miles NW of Dutch John, UT. Accessed by traveling northerly on Hwy-191 from Dutch John to Dutch John Gap; project is on W side of Hwy. · Daggett, Utah
Pinyon and juniper are encroaching into sagebrush vegetation treated for their removal in 1998. Incomplete P-J removal allowed re-encroachment. This project proposes to hand cut and lop/scatter P-J in the original 70 acres to maintain sagebrush.
Vegetation management (other than forest products)Wildlife, fish, rare plantsWatershed management
Comment Period
04/11/2012
Decision
07/2012 (Estimated)
Implementation
08/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements; Roadless Area Management; Rangeland Vegetation Improvements; Scenery Management; Watershed Improvements |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Daggett County, UT at Township 3 North, Range 22 East, portions of Sections 31, 32, and Range 21 East, portions of Section 36. |
Decision Memo · Vernal Ranger District · updated 9/13/2012
Vernal and Roosevelt Ranger Districts · Uintah, Utah
2380 acres of lodgepole pine thinning designed to release crop trees for growth. This project would have the secondary benefite of reducing fuels and improving wildife habitat for certain species.
Forest products
Decision
05/2011 (Estimated)
Implementation
06/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Lodgepole Pine Timber Sale Improvement Project | Decision Signed Date: 05/13/2011 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District; Roosevelt Ranger District |
Decision Memo · Duchesne Ranger District · updated 8/17/2012
Dry Ridge Communication site · Duchesne, Utah
Meteorological station on an existing FS Communications tower, located at the Dry Ridge Comm site.
Special use management
Comment Period
04/11/2012
Decision
07/2012 (Estimated)
Implementation
09/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Weather Station At Dry Ridge Comm. Site | Decision Signed Date: 07/26/2012 Legal Notice Date: 08/08/2012 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
Decision Memo · Vernal Ranger District · updated 8/9/2012
One drillhole in the Dyer Mountain area, near or adjacent to Forest Service road #560, in the East ½ of section 21, T1S R21E, and a second drillhole in the Grizzly Ridge area, near or adjacent to Fore · Uintah, Utah
The Proposal is to drill 2 small exploratory drillholes for locatable minerals.
Minerals and geology
Comment Period
08/03/2011
Decision
08/2012 (Estimated)
Implementation
09/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390) |
| Notice and Comment Regulation | 215 |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
Decision Memo · Ashley National Forest All Units · updated 7/26/2012
Lake Basin Area · Duchesne, Utah
Issue a Special Use Permit to install a seismograph station in the Lake Basin Area to monitor earthquake activity.
Special use management
Comment Period
04/11/2012
Decision
07/2012 (Estimated)
Implementation
09/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Seismograph Station | Decision Signed Date: 07/16/2012 Legal Notice Date: 07/24/2012 |
| Forests | Ashley National Forest |
| Districts | Ashley National Forest All Units |
| Legal Land Description | T. 2 N., R. 8 W., sec. 26, USM |
Decision Memo · Duchesne Ranger District · updated 7/11/2012
The Gilsonite Ridge area of the South Unit of the Ashley National Forest · Duchesne, Utah
The ANF proposes to permit Vantage Energy to conduct exploratory drilling and development operations for oil & gas resources within their existing leases on the South Unit of the Duchesne Dristrict.
Minerals and geology
Comment Period
05/01/2012
Decision
06/2012 (Estimated)
Implementation
10/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (3) |
| Special Authority | Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390) |
| Notice and Comment Regulation | 215 |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Vantage 2011 Oil and Gas CE Project | Decision Signed Date: 06/27/2012 Legal Notice Date: 07/03/2012 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | The 3 proposed wells would be located within the NW 1/4 of Section 5, near the center of Section 6, and within the SW 1/4 of Section 7, of township T6S R3W, Uintah Meridian. The existing Gilsonite 1- |
Decision Memo · Vernal Ranger District · updated 7/2/2012
Lower Taylor Mountain · Uintah, Utah
Removal of encroaching juniper through hand cutting/lop and scatter to enhance sage grouse habitat and sage brush communities.
Wildlife, fish, rare plantsFuels managementVegetation management (other than forest products)Watershed management
Comment Period
04/17/2012
Decision
06/2012 (Estimated)
Implementation
07/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Species Habitat Improvements; Watershed Improvements |
| Taylor Mountain Pinyon-Juniper Vegetation Management Project | Decision Signed Date: 06/13/2012 Legal Notice Date: 06/20/2012 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | Township 3 North Range 21 East, all or portions of Sections 31, 32, 33, 34 and 35 |
Decision Memo · Vernal Ranger District · updated 6/27/2012
East side of Oaks Park Reservior · Uintah, Utah
Reroute trail where soil is suitable for motorized use.
Road management
Comment Period
04/23/2012
Decision
06/2012 (Estimated)
Implementation
08/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management; Travel Management |
| Outlaw ATV Trail Reroute Project | Decision Signed Date: 06/22/2012 Legal Notice Date: 06/27/2012 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
Environmental Assessment · Roosevelt Ranger District · updated 6/13/2012
Pole Mountain Ashley National Forest Roosevelt/Duchesne Ranger District · Duchesne, Utah
The Neola North Fire in June 2007 resulted in fire-caused tree mortality. Propose salvage timber harvest of fire-killed and dying trees.
Forest products
Comment Period
08/19/2009
Decision
11/2009 (Estimated)
Implementation
07/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Timber Sales (Salvage) |
| Pole Mountain Post-Fire Timber Salvage Project | Decision Signed Date: 11/09/2009 Legal Notice Date: 11/28/2009 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | 225-acre area that burned on Pole Mountain |
Decision Memo · Roosevelt Ranger District · updated 5/8/2012
Roosevelt Ranger District · Duchesne, Utah
The Roosevelt Ranger District proposes to plant lodgepole pine or ponderosa pine seedlings in and around an area burned during the 2007 Neola North Fire.
Vegetation management (other than forest products)
Comment Period
04/03/2012
Decision
05/2012 (Estimated)
Implementation
05/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements |
| Neola North Fire Area Tree Planting Project | Decision Signed Date: 05/08/2012 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | The project area is located north of Roosevelt, Utah on Pole Mountain |
Decision Memo · Flaming Gorge Ranger District · updated 3/30/2012
one permit is located in Summit County, Utah and 8 permits located in Daggett County, Utah. · Daggett; Summit, Utah
Reauthorization of 9 special use permits
Special use management
Decision
11/2011 (Estimated)
Implementation
10/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3); 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| 9 Special Use Permits autorization and Reauthorizations | Decision Signed Date: 11/29/2011 |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
Environmental Assessment · Roosevelt Ranger District · updated 2/27/2012
Roosevelt and Duchesne Ranger District of the Ashley National Forest · Duchesne, Utah
to reduce fuels in forests (primarily Ponderosa Pine stands), brush-grass communities, and aspen-conifer vegetation types to provide additional protection to values at risk in the Rock Creek Drainage
Fuels management
Comment Period
02/21/2012
Decision
02/2012 (Estimated)
Implementation
04/2012 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements |
| Rock Creek Fuels Reduction Project | Decision Signed Date: 02/15/2012 Legal Notice Date: 02/22/2012 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T2N, R7W, Sec 25 |
Decision Memo · Vernal Ranger District · updated 10/7/2011
Approximately two miles northwest of the community of Dutch John, Utah. · Daggett, Utah
remove three passive reflectors and replace them with an 80 foot tower to provide reliable cellular service and
Special use management
Decision
10/2011 (Estimated)
Implementation
10/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Union telephone - D.J. Mountain Com. Site | Decision Signed Date: 10/05/2011 |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
Environmental Assessment · Vernal Ranger District · updated 9/7/2011
The proposed trailhead location has historically been used as a dispersed camping area and is adkacemt tp tje F;i,e Trao; approx 1/4 mi. N. of Forest boundary · Uintah, Utah
The proposal includes clearing and hardening a parking area ½ acre in size to accommodate vehicle and trailer traffic and constructing/installing a restroom facility, barriers, benches, gate, and a kiosk/information board and appropriat signing.
Recreation management
Comment Period
08/31/2011
Decision
08/2011 (Estimated)
Implementation
08/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Forest Service Energy Implementation Plan |
| Notice and Comment Regulation | 215 |
| Project Activity | Plan Amendment; Trail Management |
| Flume Trailhead Development Project | Decision Signed Date: 08/24/2011 Legal Notice Date: 08/31/2011 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | SLM, T. 2 S., R. 19 E., Sec. 36, SE ¼; 40º35'55" N, 109º43'56" W, NAD83 |
Environmental Assessment · Duchesne Ranger District · updated 8/12/2011
High Uinta Wilderness Area · Duchesne, Utah
Reauthorize grazing on three recreational livestock grazing allotments onthe Roosevelt-Duchesne District.
Grazing management
Comment Period
04/07/2009
Decision
08/2011 (Estimated)
Implementation
08/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Grazing Authorizations |
| Reauthorization of Recreation Livestock Grazing on the Grandaddy Basin, Squ | Decision Signed Date: 08/03/2011 Legal Notice Date: 08/09/2011 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
Decision Memo · Duchesne Ranger District · updated 8/3/2011
South Unit Duchesne Ranger District Ashley National Forest · Duchesne, Utah
Berry Petroleum Company (Berry) is proposing to drill up to 19 oil and natural gas wells from up to eight existing well pads on federal mineral leases the Company holds under the South Unit of the Ashley National Forest in Duchesne County, Utah.
Minerals and geology
Decision
06/2011 (Estimated)
Implementation
08/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (3) |
| Special Authority | Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390) |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Berry Petroleum 19 Directionsl Wells 2011 | Decision Signed Date: 06/10/2011 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T6S R4W, T6S R5,W., |
Environmental Assessment · Flaming Gorge Ranger District · updated 8/3/2011
Approximately seven miles east of Manila, Utah, and one mile northwest of Lucerne Valley Campground. · Daggett; Sweetwater, Utah; Wyoming
The Forest Service, Ashley National Forest, Flaming Gorge Ranger District, is preparing an Environmental Assessment for the installation of a new vault restroom at State Line Cove.
Recreation management
Comment Period
04/17/2011
Decision
07/2011 (Estimated)
Implementation
08/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Developed Site Management; Facility Improvements/Construction; Dispersed Recreation Mgmt. |
| State Line Cove Vault Restroom 2011 | Decision Signed Date: 07/25/2011 Legal Notice Date: 08/03/2011 |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Section 18, Township 3 north, Range 21 east, Salt Lake Meridian, Daggett County, Utah |
Decision Memo · Flaming Gorge Ranger District · updated 8/2/2011
Flaming Gorge National Recreation Area · Sweetwater, Wyoming
The FG Ranger District proposed to designate a portion of a user created trail as a non-motorized bike system trail. This trail will connect to a protion of a bike trail on BLM managed lands.
Recreation management
Decision
08/2011 (Estimated)
Implementation
08/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Wilkins Peak Bike Trail system Project | Decision Signed Date: 08/01/2011 |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | T.17 N., R10+ W., Section 6 |
Decision Memo · Ashley National Forest All Units · updated 6/29/2011
South Unit of the Ashley National Forest. The project area begins approximately 11 miles south of the town of Duchesne, Utah. · Duchesne, Utah
Drill up to 19 oil and natural gas wells from up to eight existing well pads on federal mineral leases that the Berry holds on the South Unit of the Ashley National Forest
Minerals and geology
Decision
06/2011 (Estimated)
Implementation
06/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (3) |
| Special Authority | Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390) |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Berry Petroleum 19 Directionsl Wells 2011 | Decision Signed Date: 06/10/2011 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Township 6 South, Range 4 West, and Township 6 South, Range 5 West |
Environmental Assessment · Duchesne Ranger District · updated 5/18/2011
D34 South Unit, from Wildhorse Ridge eastwards to Gilsonite Ridge · Duchesne, Utah
Vantage Energy proposes drilling 8 exploratory oil and gas wells within the South Unit of the Ashley National Forest. Some access roads will need upgraded, and successful sites will need added upgrades.
Minerals and geology
Comment Period
12/15/2009
Decision
05/2011 (Estimated)
Implementation
07/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Ira - Inventoried Roadless Area Activities Requiring Secretary/Undersecretary Approval |
| Notice and Comment Regulation | 215 |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Vantage Energy Uinath LLC Oil and Gas Exploration Project | Decision Signed Date: 01/26/2011 (FS Withdrawn) Legal Notice Date: 01/26/2011 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | Portions of Townships T6S R6W, T6S R5W, T6S R4W, T6S R3W, T7S R5W, and T7S |
Decision Memo · Ashley National Forest All Units · updated 5/11/2011
Flaming Gorge Ranger District Ashley, National Forest · Daggett; Sweetwater, Utah; Wyoming
In total seven Special Use Permits are proposed for reissuance under the same terms and conditions as the existing permits.
Special use managementRecreation management
Decision
01/2011 (Estimated)
Implementation
06/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3); 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Special Use Authorizations |
| Flaming Gorge Ranger District 2010 Special Use Project Proposals | Decision Signed Date: 01/10/2011 |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Multiple locations by project |
Environmental Assessment · Flaming Gorge Ranger District · updated 5/11/2011
Northwest portion of the Ashley National Forest that generally includes the Cow Hollow, Carter Military, Lodgepole Creek and Sols Canyon areas · Daggett; Summit, Utah
Treatments within North Flank area to capture the value of dead trees, to improve forest age class and species diversity, to improve forest health and vigor, to promote and maintain aspen and to reduce forest fuels.
Fuels management
Comment Period
05/14/2008
Decision
05/2011 (Estimated)
Implementation
08/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Flaming Gorge Ranger District |
Environmental Impact Statement · Ashley National Forest All Units · updated 2/24/2011
Ashley National Forest · Daggett; Duchesne; Uintah; Utah; Wasatch; Sweetwater, Utah; Wyoming
Develop motor vehicle route designations on the Forest (ALL districts and Flaming Gorge) that manage the use of off-road vehicles through the designation of routes and areas.
Recreation managementRoad management
NOI in Federal Register
11/09/2007
DEIS NOA in Federal Register
04/17/2009
FEIS NOA in Federal Register
09/21/2009
Decision
09/2009 (Estimated)
Implementation
01/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Travel Management |
| Ashley National Forest Motorized Travel Plan | Decision Signed Date: 09/09/2009 Legal Notice Date: 09/30/2009 |
| Forests | Ashley National Forest |
| Districts | Ashley National Forest All Units |
| Legal Land Description | Vernal, Roosevelt, Duchesne & Flaming Gorge Ranger Districts |
Environmental Assessment · Duchesne Ranger District · updated 2/24/2011
Farm Creek · Duchesne, Utah
Proposal to conduct exploratory drilling for locatable minerals on the existing Iron King mining claims within the Farm Creek drainage of the Ashley National Forest.
Minerals and geology
Comment Period
12/05/2009
Decision
06/2010 (Estimated)
Implementation
07/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Iron King Drilling Proposal | Decision Signed Date: 06/22/2010 Legal Notice Date: 06/22/2010 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | Section 29 of T3N R1W, Uinta Special Meridian |
Decision Memo · Roosevelt Ranger District · updated 12/21/2010
Roosevelt/Duchesne Ranger District in Forest Plan Management Areas "n" (ranage of resource uses), "e" (wildlife emphasis) and "f" (dispersed recreation roaded). · Duchesne, Utah
Improve wildlife habitat by reducing stand density for long-term forest health and sustainablility.
Vegetation management (other than forest products)
Decision
12/2010 (Estimated)
Implementation
05/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Salt Creek Ponderosa Pine Thinning (Lake Fork & Burnt Mill Spring Units) | Decision Signed Date: 12/13/2010 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | T2N R5W Sec 36 and T2N R4W Sections 31 and 32 |
Decision Memo · Vernal Ranger District · updated 11/29/2010
East park Campground area · Uintah, Utah
implement pole thinning and salvage on approximately 229 acres of lodgepole pine stands near the Eastpark campground.
Fuels management
Decision
11/2010 (Estimated)
Implementation
06/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (13), 36 Cfr 220.6(E)(13) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
Decision Memo · Ashley National Forest All Units · updated 11/29/2010
Lucerne Valley Marina is located withing Daggett County, Utah, and also lies within the Flaming Gorge National Recreation Area · Daggett; Duchesne; Summit; Uintah, Utah
This action will renew the Special Use Permit to the Flaming Gorge Corporation to operate the Lucerne Valley Marina for a period of 30 years.
Special area managementRecreation managementSpecial use management
Decision
11/2010 (Estimated)
Implementation
11/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Forests | Ashley National Forest |
| Districts | Ashley National Forest All Units |
| Legal Land Description | Lucerne Valley Marina is generally located within NW 1/4, Sec. 20, R21 E, SLM |
Decision Memo · Flaming Gorge Ranger District · updated 9/28/2010
Flaming Gorge Ranger District located within the Sheep Creek Mountain Allotment. - Utah. COUNTY - Daggett · Daggett, Utah
Improved Livestock Distribution
Grazing management
Decision
04/2010 (Estimated)
Implementation
05/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Allotment Management |
| Sheep Creek Mountain Dowd Hole Ponds Water Development | Decision Signed Date: 04/24/2010 |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
Environmental Assessment · Flaming Gorge Ranger District · updated 9/27/2010
Burnt Fork, Beaver Creek, and Uinta-Wasatch-Cacche N.F. portion of the Hickerson Park Allotment on the ANF · Duchesne, Utah
Livestock grazing will be evaluated to ensure resources are maintained or move towards site-specific desired conditions
Grazing management
Comment Period
09/22/2010
Decision
09/2010 (Estimated)
Implementation
11/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Grazing Allotment Management |
| Burnt Fork C&H, Beaver Creek C&H, and Hickerson Park C&H Allotment | Decision Signed Date: 09/14/2010 Legal Notice Date: 09/22/2010 |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | T. 2N., R17E-all or parts of sections 6, 5, 4, 3, 7, 8, 9, 10, 15, 16, 21 |
Decision Memo · Roosevelt Ranger District · updated 7/2/2010
High Uintas Wilderness Area Roosevelt Ranger District, Duchesne Ranger District. · Duchesne, Utah
Permit application to stabilize 2 mountain lakes (Deer & East Timothy) in the High Uintas Wilderness in the 2010 summer season. Construct permanent trail reroute to avoid Deer Lake Dam and provide public safety during and after dam stabilization.
Watershed managementRecreation management
Decision
04/2010 (Estimated)
Implementation
06/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| High Lakes Stabilization Swift Creek Trail Reroute Special Use Permit | Decision Signed Date: 04/16/2010 |
| 2010 High Lakes Stabilization Projects Special Use Permit Issuance | Decision Signed Date: 04/16/2010 |
| High Lakes Stabilization Project | Decision Signed Date: 04/16/2010 Legal Notice Date: 04/16/2010 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | T.3N R.4W, Sec. 8 & T.4N, R.4W, Sec.28 & 29, of the West Uintah Special Meridian. Mt. Emmons |
Decision Memo · Duchesne Ranger District · updated 7/2/2010
Salt Creek Drainage · Duchesne, Utah
Wildlife habitat improvement, forest vegetation improvement, and fuels reduction project in the Salt Creek area. The project area in 4,693 acres of which 2500-3500 acres would be mechanically treated.
Vegetation management (other than forest products)Wildlife, fish, rare plantsFuels management
Decision
07/2010 (Estimated)
Implementation
10/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements |
| Salt Creek Ponderosa Pine Thinning Project | Decision Signed Date: 07/02/2010 Legal Notice Date: 07/02/2010 |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T2N R5W, portions of sections 28-34 and 36; and T2N R4W, portions of sections 25-27, 29, 31-32, and 34-36; all Uintah Special Meridian |
Decision Memo · Vernal Ranger District · updated 4/29/2010
Dry Fork Flume Trail · Uintah, Utah
Reroute the Flume trail, adding new segments, so that it becomes one continuous route that does not require shared mixed use with the Red Cloud Loop Scenic Backway.
Recreation management
Decision
04/2010 (Estimated)
Implementation
06/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management; Travel Management |
| Dry Fork Canyon Flume Trail Reroute | Decision Signed Date: 04/09/2010 |
| Forests | Ashley National Forest |
| Districts | Vernal Ranger District |
| Legal Land Description | 40?368N, 109?4433W and 40?3635N, 109?4513W and 40?3645N, 109?4523W |
Environmental Assessment · Vernal Ranger District · updated 3/8/2010
In the Potholes watershed which encompasses the upper portions of Potholes Creek · Uintah, Utah
Prescribed fire would be used to treat approximately 5,951 acres in six areas. Hand and aerial ignition. Chainsaws used to create fuel breaks to protect grazing and recreational improvements.
Fuels management
Decision
12/2009 (Estimated)
Implementation
04/2010 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Hfra Title I: Threats To Ecosystem Components (Such As Insect Or Disease Epidemics) |
| Notice and Comment Regulation | 218 |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Ashley National Forest |
| Districts | Duchesne Ranger District |
| Legal Land Description | T1N, R23E, all or portions of sections 26,27,34,35 and T1S, R22E all or portions of sections 1,2,3,10,11,12,13,14,15 |
Environmental Assessment · Flaming Gorge Ranger District · updated 6/10/2009
Little Elk Summit area including Young's Spring, Elk Park, and Honslinger Units · Daggett, Utah
Reduce hazardous fuels in approximately 4500 acres in the project area with the use of prescribed fire. The project will also reduce encroaching conifers in an area of the project up to 1000 acres.
Fuels management
Comment Period
02/25/2009
Decision
06/2009 (Estimated)
Implementation
10/2009 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Forests | Ashley National Forest |
| Districts | Flaming Gorge Ranger District |
| Legal Land Description | Elk Park units (1 & 2), Young's Spring unit (3), and Honslinger units (4 & 5) |
Decision Memo · Duchesne Ranger District · updated 3/20/2007
In the Strawberry Peak and Shotgun Draw area of the South Unit of the Ashley National Forest, · Duchesne, Utah
Avalon is proposing to conduct approximately 12.75 miles of 2D seismic exploration during late summer of 2006. Recording sensors and shotholes would be placed along the seismic lines. Shotholes would be drilled and shot.
Minerals and geology
Comment Period
05/16/2006
Decision
01/2007 (Estimated)
Implementation
06/2007 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Avalon 2007 Seismic Project | Decision Signed Date: 01/04/2007 |
| Decision Memo Avalon 2007 Seismic Project | Decision Signed Date: 01/04/2007 Legal Notice Date: 01/04/2007 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District; Duchesne Ranger District |
Detail fetch failed: 404 Client Error for https://www.fs.usda.gov/r04/ashley/projects/57137
Ashley National Forest All Units
Two stream crossings in the Round Park area will be upgraded with hardened ford structures in order to stop the degradation of fish habitat.
Wildlife, fish, rare plants