Decision Memo Completed

Lowline Trail New Construction

Ashley National Forest Daggett, Utah Flaming Gorge Ranger District

Approximately 0.5 miles of new non-motorized trail construction to replace a section of the current Lowline Trail.

Location

The trail construction would occur adjacent to the Lowline Trailhead parking lot near the Cedar Springs sewer lagoons in the Flaming Gorge National Recreation Area (NRA).

Project timeline

1
Scoping Start
04/25/2024
2
Decision
06/2024 (Estimated)
3
Implementation
08/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management
Lowline Trail New ConstructionDecision Signed Date: 06/21/2024
ForestsAshley National Forest
DistrictsFlaming Gorge Ranger District
Legal Land DescriptionNot Applicable
Recreation management