A new Plan of Operations was submitted for continued operations at the Honeycomb Mine. Large blocks of decorative calcite will be removed from the mine. Up to 2.5 acres active disturbance proposed. Disturbed areas not needed would be reclaimed.

Location

The Honeycomb Mine is within the Blind Stream drainage of the Duchesne District of the Ashley NF. At the end of Forest System road 121, in the North 1/2 of Section 28, T2N R8W, Uinta Meridian.

Project timeline

1
Scoping Start
03/19/2015
2
Comment Period
12/08/2015
3
Objection Period Start
02/02/2016
4
Decision
05/2016 (Estimated)
5
Implementation
06/2016 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityMinerals Or Geology Plans Of Operations
Honeycomb Mine ProjectDecision Signed Date: 05/11/2016