Yellowstone Creek's main channel became altered during a recent flood event. The new location of the channel provides a hazard to the Riverview Campground. Work would be completed using rock barbs to restore flow patterns in the former channel.
Location
North of Riverview Campground off of forest road 124
Project timeline
1
Scoping Start
07/28/2017
2
Decision
08/2018 (Estimated)
3
Implementation
08/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (19), 36 Cfr 220.6(E)(19) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Riverview Campground Bank Stabilization CE | Decision Signed Date: 08/17/2018 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | T2N R4W Section 9 NENE Uintah Basin Special Meridian |