Decision Memo Completed

Riverview Campground Stabilization

Ashley National Forest Duchesne, Utah Ashley National Forest All Units

Yellowstone Creek's main channel became altered during a recent flood event. The new location of the channel provides a hazard to the Riverview Campground. Work would be completed using rock barbs to restore flow patterns in the former channel.

Location

North of Riverview Campground off of forest road 124

Project timeline

1
Scoping Start
07/28/2017
2
Decision
08/2018 (Estimated)
3
Implementation
08/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (19), 36 Cfr 220.6(E)(19)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityWatershed Improvements
Riverview Campground Bank Stabilization CEDecision Signed Date: 08/17/2018
ForestsAshley National Forest
DistrictsRoosevelt Ranger District
Legal Land DescriptionT2N R4W Section 9 NENE Uintah Basin Special Meridian
Watershed managementFacility management