We are proposing to construct hiking trail reroutes at 7 selected locations in the Swift Creek Focus Watershed. The project would total approximately 4,600 feet of trail construction and 3,300 feet of trail closures and rehabilitation.
Location
Seven locations in the Swift Creek Watershed.
Project timeline
1
Scoping Start
04/02/2013
2
Decision
04/2014 (Estimated)
3
Implementation
06/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management; Watershed Improvements; Wilderness Management |
| Swift Creek Watershed Trail Relocations Decision Memo | Decision Signed Date: 04/24/2014 |
| Forests | Ashley National Forest |
| Districts | Roosevelt Ranger District |
| Legal Land Description | SE, Sec 20, T3N, R4W; SW, SE, Sec 5, T3N, R4W; NW, NW, Sec 5, T3N, R4W; NW, SE, Sec 32, T4N, R4W; NE, NE, Sec 32, T4N, R4W; NW, NE, Sec 4, T3N, R4W; SE, SW, Sec 4, T3N, R4W Uintah Base Meridian |